An MRP project team leader should report to the:

A
Division President.
B
Vice-President, Manufacturing
C
Plant Manager.
D
Steering Committee

答案解析

正确答案:D

解析:

The steering committee should consist of high level management representing different functions. The project team would report to the steering committee through the project manager.
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

Which of the following situation is true when capacity requirements planning determines that the load at a work center is within the capacity for the period?

单选题

A work center has an utilization of 90% and an efficiency of 95%, over the past months it has produced quantities of 600, 610, 640 and 630 per week. What is the demonstrated capacity of the work center?

单选题

The gateway work center performs the operation

单选题

A work center that is designated to produce a single item or a limited number of similar items is said to have

单选题

Using the information provided, what is the rated capacity of the work center?
Hours available: 7.2
Internal setup hours: 0.2
Standard hours produced: 7.0
Actual hours worked: 7.1
Scheduled downtime hours: 0.8
Hours per shift: 8
Shifts per day: 1
Days per week: 5.5
Number of resources: 20

单选题

The difference between capacity information used for capacity requirements planning as opposed to RCCP is

单选题

Which scheduling technique assumes that there will always be sufficient capacity and computes the schedule starting with the due date for the order?

单选题

Capacity requirements planning has been used to check the validity of the material plan, and no constraining work centers were identified, which of the following scenarios is most likely the reason?

单选题

A company is going to begin an aggressive sales promotion for a new MTS product line that will affect most work centers. Capacity requirements planning can be best be used to

单选题

Work center data:
Machines=3
Shifts per day=1
Days worked per week=5
Hours worked per shift=8
Utilization=85%
Operator efficiency=95%
Using the information provided, if the load for next week is 110 hours, the work center is

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码