Work center data:
Machines=3
Shifts per day=1
Days worked per week=5
Hours worked per shift=8
Utilization=85%
Operator efficiency=95%
Using the information provided, if the load for next week is 110 hours, the work center is
答案解析
相关题目
In a net change MRP system, which of the following transactions will cause the system to replan the part?
I. Change in the bill of materials
II. Inventory write off
III. Unexpected demand for the part
IV. Change in the lead time
Which of the following best describes the process of order launching?
An MRP system provides all of the following to the shop floor control system EXCEPT:
Which of the following is true regarding interlevel equilibrium?
I. The gross requirements correspond to the planned order release of its parent
II. Maintaining interlevel equilibrium requires partial explosions
III. It is a characteristic of regenerative MRP
Which of the following are reasons for using modular bills of material?
I. Disentangle option combinations
II. Segregate common from unique parts
Which of the following is true regarding pseudo bills of material?
I. They are never manufactured.
II. They are for transient assemblies.
III. They facilitate planning.
In an MRP implementation, which of the following methods are preferable in the cut-over phase?
All of the following are user responsibilities in maintaining an MRP system EXCEPT:
The time periods of the master production schedule must be identical to the:
An MRP project team leader should report to the: