The difference between capacity information used for capacity requirements planning as opposed to RCCP is
答案解析
解析:
More work centers are checked, but key work centers are included in both;
相关题目
Which of the following are reasons for using modular bills of material?
I. Disentangle option combinations
II. Segregate common from unique parts
Which of the following is true regarding pseudo bills of material?
I. They are never manufactured.
II. They are for transient assemblies.
III. They facilitate planning.
In an MRP implementation, which of the following methods are preferable in the cut-over phase?
All of the following are user responsibilities in maintaining an MRP system EXCEPT:
The time periods of the master production schedule must be identical to the:
An MRP project team leader should report to the:
Which of the following is true regarding phantom bills of material and phantom parts?
I. It is a bill of material for a transient assembly.
II. A phantom is never closed to or issued from stock.
In a net change MRP system, all of the following can trigger a re-planning run except:
I. Changes in product structure
II. Inventory on-hand balance adjustments
III. Changes in lead time
Which of the following distinguishes a regenerative MRP system from a net change MRP system?
I. The frequency of the re-planning cycle
II. The technique used by the system to replan parts
A customer cancels an order for 1000 units. The planner processes a transaction to reduce gross requirements by 1000 which immediately initiates a replan by MRP. Which MRP system is being used?
I. Regenerative
II. Net Change