Which of the following distinguishes a regenerative MRP system from a net change MRP system?
I. The frequency of the re-planning cycle
II. The technique used by the system to replan parts
答案解析
解析:
相关题目
Understanding the human and environmental aspects and impacts during the life of a product, process or service is called
The timing of project tasks and completion dates is displayed in a
Sources of load on work centers in a job shop include
Which of the following situation is true when capacity requirements planning determines that the load at a work center is within the capacity for the period?
A work center has an utilization of 90% and an efficiency of 95%, over the past months it has produced quantities of 600, 610, 640 and 630 per week. What is the demonstrated capacity of the work center?
The gateway work center performs the operation
A work center that is designated to produce a single item or a limited number of similar items is said to have
Using the information provided, what is the rated capacity of the work center?
Hours available: 7.2
Internal setup hours: 0.2
Standard hours produced: 7.0
Actual hours worked: 7.1
Scheduled downtime hours: 0.8
Hours per shift: 8
Shifts per day: 1
Days per week: 5.5
Number of resources: 20
The difference between capacity information used for capacity requirements planning as opposed to RCCP is
Which scheduling technique assumes that there will always be sufficient capacity and computes the schedule starting with the due date for the order?
