Planning bills are referred to as pseudo bills. This reference occurs because they:

A
are modular bills of materials.
B
represent bill structures of parts that cannot be built.
C
are manufacturing bills used in final assembly.
D
facilitate capacity planning.

答案解析

正确答案:B

解析:

Pseudo bills are planning bills of material which facilitate planning by assigning percentages to the options for a product. They are for products which are not being built.