At one time a high-end automobile had 97 components, after an out-of-the-box evaluation, the number was reduced to 7 parts, this part reduction is a key goal of
答案解析
解析:
**Supplier rationalization, also known as supply base reduction [SBR] is the process of shrinking the supply base by reducing the number of active suppliers. The primary agenda of supplier rationalization is to streamline the organization's spend to fewer suppliers and driver better value from those relationships.
相关题目
Which of the following statements is true about the master production schedule?
The use of modular bills of material allows the master production schedule to:
A final assembly schedule is the final schedule of what will be assembled to meet the customers order. The final assembly schedule should be completed:
All of the following benefits result from master scheduling EXCEPT:
Planning bills are referred to as pseudo bills. This reference occurs because they:
All of the following are outputs from the Sales and Operations Planning process EXCEPT:
Master schedule changes inside the firm zone must be managed. These changes should be authorized by the:
Which of the following functions should be involved with the development of the production plan?
I. Marketing
II. Manufacturing
III. Finance
Which of the following would be a symptom of a mismanaged master schedule?
I. The capacity plan is level loaded.
II. The on-time delivery rate is less than 90%.
III. Lead times in the factory are excessively short.
IV. Past due shop orders occasionally occur.
Which of the following statements are true regarding master scheduling?
I. In make-to-stock production environments, component assembly lead time is firm.
II. In make-to-order production environments, final assembly lead time is firm.
III. In assemble-to-order production environments, assembly lead time is firm.
IV. In make-to-stock production environments, order process and shipping lead times are free.