Which of the following approaches to managing engineering changes is the most disruptive to manufacturing?

A
Holding all changes until the product in production
B
Introducing changes during prototype runs
C
Including the supplier in engineering change decisions
D
Establishing an engineering change committee

答案解析

正确答案:A

解析:

Engineering changes can be very expensive and are best handled as they arise, rather than a complete overhaul after production has begun;
题目纠错
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

Planning bills are referred to as pseudo bills. This reference occurs because they:

单选题

All of the following are outputs from the Sales and Operations Planning process EXCEPT:

单选题

Master schedule changes inside the firm zone must be managed. These changes should be authorized by the:

单选题

Which of the following functions should be involved with the development of the production plan?
I. Marketing
II. Manufacturing
III. Finance

单选题

Which of the following would be a symptom of a mismanaged master schedule?
I. The capacity plan is level loaded.
II. The on-time delivery rate is less than 90%.
III. Lead times in the factory are excessively short.
IV. Past due shop orders occasionally occur.

单选题

Which of the following statements are true regarding master scheduling?
I. In make-to-stock production environments, component assembly lead time is firm.
II. In make-to-order production environments, final assembly lead time is firm.
III. In assemble-to-order production environments, assembly lead time is firm.
IV. In make-to-stock production environments, order process and shipping lead times are free.

单选题

Which of the following are objectives of the master schedule?
I. A level repeating schedule
II. Changes are kept to a minimum
III. The schedule sums to the production plan
IV. Maintain planning bills

单选题

Which of the following statements are true regarding the final assembly schedule?
I. It is a statement of the exact set of end products to be built.
II. It controls the manufacturing from fabricated products to shippable products.
III. It schedules the purchase of components not under MPS control which are needed for final assembly.

单选题

The rough-cut capacity plan will differ from the resource plan in which of the following ways?
I. The rough-cut capacity plan is less detailed than the resource plan.
II. The rough-cut capacity plan considers more production resources.
III. Lead times are offset in the rough-cut capacity plans.
IV. Rough-cut plans are displayed in months or quarters.

单选题

In which of the following environments will the final assembly schedule normally correspond to the MPS?
I. Make-to-stock
II. Make-to-order
III. Assemble-to-order

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码