A line works 8 hour shift per day, 5 days a week. If the demand is 960 units per day, the takt time is

A
0.5 min
B
2.5 min
C
12.5 min
D
0.04 min

答案解析

正确答案:A
题目纠错
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

If the sum of the forecast errors is 100 for four periods, what should the safety stock level be for a 95% service level? (Round to nearest whole number)

单选题

Every company should have a set of functional plans synchronizing activities across functions that specify production levels, capacity levels, staffing levels, funding levels, etc. to achieve the intermediate goals and objectives of the organization. This plan would be called the:

单选题

A distribution network structure is the:

单选题

In a make-to-stock company, distribution will divide the number of items (or dollars) shipped by the number of items (or dollars) that were supposed to ship. This measure is called the:

单选题

Which of the following environments would have the lowest production volume of each sales unit?

单选题

Which of the following is not a key element of demand management?

单选题

Which of the following is the primary role for demand management?

单选题

In a manufacturing facility, the MRP system uses the manufacturing lead time to calculate the start time of an order. In a DRP system, the lead time used in the system is the:

单选题

The forecasting system that uses the one forecasting model that would have performed best in the recent past to generate the next forecast is:

单选题

If a company increases the number of distribution centers, which of the following will usually occur?
I. Aggregate safety stock will increase
II. Aggregate cycle time will decrease
III. Transportation inventories will increase

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码