AI智能推荐题库-试题通 AI智能整理导入题库-试题通
×
首页 题库中心 CPIM PART2-供应链资格认证考试 题目详情
C93BF00FBEF00001B89720C0D4CE1712
CPIM PART2-供应链资格认证考试
3,028
单选题

In a standard cost environment, which of the following labor reporting is most important to a continuous improvement program?

A
actual setup hours
B
standard production order hours
C
Standard internal setup hours
D
Actual run hours

答案解析

正确答案:D

解析:

Actual run hours can be compared to standard to determine variance;
Actual setup could be both internal and external setup. Changing of standard hours are long term in nature;
题目纠错
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

At times, data used to forecast will be of poor quality. Which of the following would be the correct action for the stated data quality problem?
I. Filter and adjust for abnormal demand
II. Accept data omissions and plan around them
III. Accept normal variations in the data
IV. Substitute for data omissions

单选题

The production forecast:

单选题

Listed below is the history of demand for a product.
Forecast for May: 100
Actual May: 150
Actual June: 155
Actual July: 140
Actual August: 153
Using single exponential smoothing with an alpha of .10, what would the smoothed average be at the end of August?

单选题

What should the level of accuracy be in a forecast?

单选题

In deciding which forecasting technique to use, a company's management must take many factors into account. Which of the following must be considered?
I. The cost versus the value of the forecast
II. The order promising policy
III. The degree of accuracy necessary

单选题

A panel of experts are assembled and asked to fill out questionnaires about your business. The questionnaires are then used to produce another set of questionnaires which are then distributed to the panel again. Which forecasting method is being used?

单选题

Long-range forecasts are associated with which of the following techniques?
I. A small number of products or families
II. Recurring or periodic data
III. Qualitative techniques are used more frequently than short range forecasts
IV. External data

单选题

If the sum of the forecast errors is 100 for four periods, what should the safety stock level be for a 95% service level? (Round to nearest whole number)

单选题

Every company should have a set of functional plans synchronizing activities across functions that specify production levels, capacity levels, staffing levels, funding levels, etc. to achieve the intermediate goals and objectives of the organization. This plan would be called the:

单选题

A distribution network structure is the:

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码