The following information is available for a work center. It is now day 150. Using the priority rule of critical ratio, what is the desired job sequence?
Job Arrival sequence Processing hours Date due Work days remaining
A 1 5 156 4
B 3 3 153 3
C 2 2 152 1
D 4 4 152 3
E 5 1 155 2

A
A B C D E
B
E C B D A
C
D B A C E
D
C E B D A

答案解析

正确答案:C
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

In order to effectively support manufacturing, purchasing must have software systems which integrate to the manufacturing planning and control system. Some of the elements of this system should include:
I. Purchases of components or raw materials based on supplier scheduling
II. Information for the buyer
III. Performance measures for analysis
IV. Simulation capability

单选题

Hamel discusses 10 principles that can help a company free its "revolutionary spirit. All of the following are principles of strategic revolution EXCEPT:

单选题

Kapp writes about the four levels of training evaluation. Evaluations which test participant learning is:

单选题

Which of the following would best describe the purpose of the Quick Response movement?

单选题

A change effort needs motivated people to "buy in" to the need for change in the company. The best possible way to develop the need for change is to:

单选题

If a company is going to manufacture items during the slack season for use during a busy season, the items chosen should be:

单选题

In which of the following environments will a statistical order point system work best?

单选题

There are three approaches to rough cut capacity planning. Which of the following is NOT an approach to RCCP?

单选题

Which of the following best describes the number of resources to be checked during a rough cut capacity planning process?

单选题

All manufacturing companies should run a resource requirements plan at the production plan level. However, many companies should also run a rough cut capacity plan at the MPS level as well. Which of the following types of companies should also run a rough cut capacity plan at the MPS level?

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码