There are three approaches to rough cut capacity planning. Which of the following is NOT an approach to RCCP?
答案解析
解析:
相关题目
Variations in product design, process requirements, or order quantities, require which of the following manufacturing processes?
All of the following are considerations in the adoption of a process focus EXCEPT the
Which of the following production layouts will most likely contain dedicated lines?
Which of following capabilities of finite loading is most important in an environment where routings use many of the same work centers?
Which of the following actions should dispatcher perform in an environment where there is excess capacity, in order to meet a shortage at a downstream operation?
Overlapping is used to compress lead time by
Which of the following elements would have the most impact on reducing manufacturing lead time?
The following information is available for a work center. It is now day 150. Using the priority rule of critical ratio, what is the desired job sequence?
Job Arrival sequence Processing hours Date due Work days remaining
A 1 5 156 4
B 3 3 153 3
C 2 2 152 1
D 4 4 152 3
E 5 1 155 2
A company produces a high-volume electronic assembly using a series of dedicated production lines. This is an example of which process environment?
Which of the following conditions typically is necessary for a successful pull production system implementation?