All manufacturing companies should run a resource requirements plan at the production plan level. However, many companies should also run a rough cut capacity plan at the MPS level as well. Which of the following types of companies should also run a rough cut capacity plan at the MPS level?

A
Low variety of product mix
B
High variety of product mix
C
High volume, make to stock
D
Low volume, engineer to order

答案解析

正确答案:B

解析:

Companies with a high variety of product mix may require a rough cut capacity plan at the MPS level because the variety of products scheduled may change dramatically the capacity needed for the plan. The production plan level may not adequately capture this variety. In order to accomplish the MPS rough cut capacity plan, the MPS would be exploded through the item resource profile to generate the required capacity to meet the MPS.
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

A direct handoff from one operation to the next such as a customer and supplier located in the same facility will

单选题

A company has a number of products that are similar, but are subject to unstable demand patterns. The company desire to implement a program to reduce inventory investment while providing a maximum 3-day customer order turnaround. Which of the following manufacturing environment is most applicable to meet that goal?

单选题

Variations in product design, process requirements, or order quantities, require which of the following manufacturing processes?

单选题

All of the following are considerations in the adoption of a process focus EXCEPT the

单选题

Which of the following production layouts will most likely contain dedicated lines?

单选题

Which of following capabilities of finite loading is most important in an environment where routings use many of the same work centers?

单选题

Which of the following actions should dispatcher perform in an environment where there is excess capacity, in order to meet a shortage at a downstream operation?

单选题

Overlapping is used to compress lead time by

单选题

Which of the following elements would have the most impact on reducing manufacturing lead time?

单选题

The following information is available for a work center. It is now day 150. Using the priority rule of critical ratio, what is the desired job sequence?
Job Arrival sequence Processing hours Date due Work days remaining
A 1 5 156 4
B 3 3 153 3
C 2 2 152 1
D 4 4 152 3
E 5 1 155 2

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码