AI智能推荐题库-试题通 AI智能整理导入题库-试题通
×
首页 题库中心 CPIM PART2-供应链资格认证考试 题目详情
C93BF00FBEF00001B89720C0D4CE1712
CPIM PART2-供应链资格认证考试
3,028
单选题

Kapp writes about the four levels of training evaluation. Evaluations which test participant learning is:

A
Level 1
B
Level 2
C
Level 3
D
Level 4

答案解析

正确答案:B

解析:

Level 2 evaluation can include a test or a demonstration of the skills which were learned. The intent is to determine if the participant can pass a test demonstrating what he/she has learned. The APICS certification exams are a level 2 test.
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

Overlapping is used to compress lead time by

单选题

Which of the following elements would have the most impact on reducing manufacturing lead time?

单选题

The following information is available for a work center. It is now day 150. Using the priority rule of critical ratio, what is the desired job sequence?
Job Arrival sequence Processing hours Date due Work days remaining
A 1 5 156 4
B 3 3 153 3
C 2 2 152 1
D 4 4 152 3
E 5 1 155 2

单选题

A company produces a high-volume electronic assembly using a series of dedicated production lines. This is an example of which process environment?

单选题

Which of the following conditions typically is necessary for a successful pull production system implementation?

单选题

A small past-due load often exists at a certain work station. Otherwise, past due loads move around the facility based on product volume and mix. This is an indication that the work station

单选题

A demand-pull facility produces five versions of an end item with FAS. Which of the following elements must be accounted for when scheduling a dedicated final assembly line?

单选题

Loading leveling has which of the following benefits for scheduling?

单选题

Which of the following capacity management techniques calculates the capacity at a work center in a time period without considering the capacity available?

单选题

Which of the following changes would have an impact on the use of a production activity control system?
1. Changing from a batch to a line manufacturing environment;
2. Implementing modular BOM for items with options;
3. Grouping production equipment into focused work cells;

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码