In order to effectively support manufacturing, purchasing must have software systems which integrate to the manufacturing planning and control system. Some of the elements of this system should include:
I. Purchases of components or raw materials based on supplier scheduling
II. Information for the buyer
III. Performance measures for analysis
IV. Simulation capability
答案解析
相关题目
The following information is available for a work center. It is now day 150. Using the priority rule of critical ratio, what is the desired job sequence?
Job Arrival sequence Processing hours Date due Work days remaining
A 1 5 156 4
B 3 3 153 3
C 2 2 152 1
D 4 4 152 3
E 5 1 155 2
A company produces a high-volume electronic assembly using a series of dedicated production lines. This is an example of which process environment?
Which of the following conditions typically is necessary for a successful pull production system implementation?
A small past-due load often exists at a certain work station. Otherwise, past due loads move around the facility based on product volume and mix. This is an indication that the work station
A demand-pull facility produces five versions of an end item with FAS. Which of the following elements must be accounted for when scheduling a dedicated final assembly line?
Loading leveling has which of the following benefits for scheduling?
Which of the following capacity management techniques calculates the capacity at a work center in a time period without considering the capacity available?
Which of the following changes would have an impact on the use of a production activity control system?
1. Changing from a batch to a line manufacturing environment;
2. Implementing modular BOM for items with options;
3. Grouping production equipment into focused work cells;
Increased flexibility in order to meet customer demand changes can be achieved by
Material consumed in a pull environment is determined by