All of the following are user responsibilities in maintaining an MRP system EXCEPT:
答案解析
解析:
相关题目
The gateway work center performs the operation
A work center that is designated to produce a single item or a limited number of similar items is said to have
Using the information provided, what is the rated capacity of the work center?
Hours available: 7.2
Internal setup hours: 0.2
Standard hours produced: 7.0
Actual hours worked: 7.1
Scheduled downtime hours: 0.8
Hours per shift: 8
Shifts per day: 1
Days per week: 5.5
Number of resources: 20
The difference between capacity information used for capacity requirements planning as opposed to RCCP is
Which scheduling technique assumes that there will always be sufficient capacity and computes the schedule starting with the due date for the order?
Capacity requirements planning has been used to check the validity of the material plan, and no constraining work centers were identified, which of the following scenarios is most likely the reason?
A company is going to begin an aggressive sales promotion for a new MTS product line that will affect most work centers. Capacity requirements planning can be best be used to
Work center data:
Machines=3
Shifts per day=1
Days worked per week=5
Hours worked per shift=8
Utilization=85%
Operator efficiency=95%
Using the information provided, if the load for next week is 110 hours, the work center is
In a job shop environment, the technique that results in a short-term planned set of projected completion times for operations and simulated queue levels is
Which of the following routing data do both infinite CRP and finite scheduling use for planning and scheduling