A scheduling technique that considers slack time to increase or decrease the calculated lead time of an order is
答案解析
解析:
For backward scheduling, slack time is the difference between the latest start date and the earliest start date; For forward scheduling, it the difference between the earliest completion date and the latest completion date, therefore, slack time provides an element of flexibility in planning, positive slack time allows an increase in lead time while negative slack time requires that it be shortened, in probable scheduling, we take slack time into account to increase or decrease lead time;
For Probable scheduling, the operations are distributed evenly between the earliest start date and the latest completion date, then the start or completion date of each operation is its probable start date or problem completion date;
相关题目
Advanced planning and scheduling systems determine the optimal schedule by eliminating:
A process train is a representation of the flow of materials through a process industry manufacturing system. Within this process train, equipment that performs a basic manufacturing step, such as mixing or packaging is called a:
In a flow factory, the capacity of a work cell would be established by:
In order for manufacturing planning systems to work properly, lead times in the system must be dependable. This means that queues must be under control. There are three reasons why queues are out of control. Which of the following is NOT a reason for out of control queues?
Using the "bath tub" to represent a work center, the water in the tub would represent:
Capacity requirements planning (CRP) differs from rough cut capacity planning (RCCP) in four respects. Which of the following is not a difference between CRP and RCCP?
The capacity requirements process is an infinite loading technique. This means that:
Which of the following would be an objective of capacity requirements planning?
The ability of a system to automatically trace the requirements for a given component up the bill structure to the source of the requirement is referred to as:
Planning factors used in the item master record include all of the following EXCEPT: