Which of the following would be an objective of capacity requirements planning?

A
Calculation of the materials needed to meet the schedule
B
Determining the machines needed to complete the MPS
C
Maintaining the priority of the order in relation to other orders
D
Providing feedback to the production plan regarding its reasonability

答案解析

正确答案:B

解析:

Capacity requirements planning is a detailed look at each machine and the load on the capacity of those machines. It does not determine the materials needed nor does it provide feedback to the production plan as it is too detailed for the production plan to use. Also, the priority of the orders are maintained by the MRP system.
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

A call center operates with 130 customer service representatives, in an 8 hour period. The company receives 8000 calls per day and the average call takes 7 minutes, the utilization of the call center is

单选题

The amount of scheduled work ahead of a manufacturing facility expressed in terms of hours of work or units of production is called

单选题

Run time = 15 minutes per piece
Setup time = 1 hour
Queue time = 8 hours
Move time = 8 hours
Quantity of order = 28 pieces
Using the information provided, calculate the total capacity requirement for a work center in hours;

单选题

A new product is being introduced to the company's product mix, which will have an effect on the current period material plan due to the cumulative lead time of the purchased parts. Which of the following actions would be of immediate value to the material planner?

单选题

Utilization is the ratio of

单选题

A press is used to stamp left and right-hand door panels simultaneously from a roll of sheet metal. The relationship between those two parts is

单选题

Which of the following statements describes how capacity planning provides feedback to material planning for scheduling operations?

单选题

A scheduling technique that considers slack time to increase or decrease the calculated lead time of an order is

单选题

The ability of manufacturing to respond quickly to external or internal changes is

单选题

Loads in CRP in a well-run company are fairly balanced in the short-term but are dropping off later in the planning horizon. The most likely reason is

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码