Capacity requirements planning (CRP) differs from rough cut capacity planning (RCCP) in four respects. Which of the following is not a difference between CRP and RCCP?
答案解析
解析:
相关题目
Run time = 15 minutes per piece
Setup time = 1 hour
Queue time = 8 hours
Move time = 8 hours
Quantity of order = 28 pieces
Using the information provided, calculate the total capacity requirement for a work center in hours;
A new product is being introduced to the company's product mix, which will have an effect on the current period material plan due to the cumulative lead time of the purchased parts. Which of the following actions would be of immediate value to the material planner?
Utilization is the ratio of
A press is used to stamp left and right-hand door panels simultaneously from a roll of sheet metal. The relationship between those two parts is
Which of the following statements describes how capacity planning provides feedback to material planning for scheduling operations?
A scheduling technique that considers slack time to increase or decrease the calculated lead time of an order is
The ability of manufacturing to respond quickly to external or internal changes is
Loads in CRP in a well-run company are fairly balanced in the short-term but are dropping off later in the planning horizon. The most likely reason is
If a work center is overstated in terms of available production capacity
Which type of capacity is the best indicator that the material plan is infeasible if it equals the required capacity at a particular work center?