Company ABC is trying to calculate how much safety stock they should have for their highest selling product. With the following info calculate the safety stock.
Standard Deviation = 25
Safety Factor = 4.00
Lead Time = 4 weeks
Forecast of 250 per week
答案解析
解析:
Forecast Period) =25*4*2=200
Note: Because forecast was in weeks and lead time was also shown in weeks then the forecast period
would be set as 1
相关题目
A component has 3 qualified suppliers, but none has been designated as the primary supplier, which of the following lead times should be used for MRP in order to ensure delivery reliability?
In an ETO environment, what determines the latest point at which the BOM can be completed and released to MRP?
The primary purpose of the BOM in the MRP process is
Pegging is used to
Which of the following features are characteristic of continuous process manufacturing?
1. Low-cost production
2. Multipurpose process technology
3. Price as an order-winning criterion
4. Narrow product range
A company makes products with multiple options and is experiencing a temporary increase in sales, which of the following inventories should be in store?
MRP has calculated a gross demand of 50 units in period 4. The net requirement and safety stock are 0. The order quantity is 100 units, if the next net demand is 20 units in period 6.
A material planner is most likely to need to take manual action if
To override the MPR logic for quantity or date of a planned orders, the planner should use
A performance objective of MRP would be a reduction of