In an ETO environment, what determines the latest point at which the BOM can be completed and released to MRP?

A
Point at which the parent BOM is completed
B
Point where the FAS is completed
C
Demand horizon from the MPS
D
Longest lead time horizon to obtain any required components

答案解析

正确答案:D

解析:

The longest lead time ensures that sufficient lead time is provided if that supplier is selected, if the other supplier is selected they receive an order with additional lead time to deliver;