An MRP system provides all of the following to the shop floor control system EXCEPT:
答案解析
解析:
相关题目
Capacity requirements planning has been used to check the validity of the material plan, and no constraining work centers were identified, which of the following scenarios is most likely the reason?
A company is going to begin an aggressive sales promotion for a new MTS product line that will affect most work centers. Capacity requirements planning can be best be used to
Work center data:
Machines=3
Shifts per day=1
Days worked per week=5
Hours worked per shift=8
Utilization=85%
Operator efficiency=95%
Using the information provided, if the load for next week is 110 hours, the work center is
In a job shop environment, the technique that results in a short-term planned set of projected completion times for operations and simulated queue levels is
Which of the following routing data do both infinite CRP and finite scheduling use for planning and scheduling
Which of the following reporting points is of use when determining run times?
A work center is consistently overloaded to the point where overtime is required nightly and on weekends. This seems to be a problem for only this work center. The most likely reason is
Before delaying a master schedule item to balance load with capacity in a MTO environment, the planner should first check the
The manufacturing environment best suited for the introduction phase of a product's life cycle is
A company uses rated capacity for capacity requirements planning, which of the following statements is true?