Which of the following capacity planning (load) report characteristics can be attributed to MRP?
I. load is based on both planned and open orders;
II. Load reflects valid order priorities;
III. Load distribution is based on actual lead times;
答案解析
解析:
III is incorrect because load distribution is based on planned and not actual times;
相关题目
Which of the following consequences is a result of inaccurate inventory data?
During the define phase of a six sigma project, which of the following activities takes place?
Important and measurable characteristics of a product or process whose performance targets are set by customer is
When attempting to understand whether there is a relationship between 2 variables, which quality control tool should be used?
After come investigation, a packaging company determined that all of its defective containers were being delivered by one of their third-party trucking companies. What quality tool would have been used to find this information?
Structured problem solving providers what essential result to an organization?
A company has implemented a corrective action to one for the 4 production lines. Before implementing the change to the other lines, which of the following action should be taken?
A company has successfully completed improvement projects in several business units. Which of the following breakthroughs would be achieved when the improvements are embedded into the entire organization?
A manufacture is experiencing expensively long setup times and first-piece inspection. Which of the following areas should be examined first?
Which of the following approaches provides the reliability necessary to support a tightly integrated manufacturing operation?