Standard hours/part=0.1
Standard hours expected=7.2
Standard internal setup time=0.25 hours
Scheduled downtime=0
Actual run time=7 hours
Actual internal setup time=0.1hour
Total hours/shift=8
Resources=1
Shift/day=1
The utilization for the work center is
答案解析
解析:
相关题目
Variations in product design, process requirements or order quantities, require which of the following manufacturing processes?
Which of the following product layout will most likely contain dedicated lines?
Which of the following elements would have the most impact on reducing manufacturing lead time?
Which of the following changes would have an impact on the use of a production activity control system?
1. Changing from a batch to a line manufacturing environment;
2. Implementing modular bill of material for items with options;
3. Grouping production equipment into focused work cells;
Load leveling has which of the following benefits for scheduling?
Material consumed in a pull environment is determined by
Which of the follow aspects of a job most determine the day and time when it will be done?
Which of the following situations is most likely a reason for establishing order priorities with a FAS based on the internal measures, rather than on customer-oriented measures?
Which of the following orders will production have the most of for planning and scheduling in an ATO environment?
Which of the following techniques is used in a push system but not in a pull system to ensure that inventory is available for an order prior to release to a work center?