单选题

Which of the following benefits of setup reduction is most immediate?

A
improved quality
B
Reduced queue time
C
Reduced product cost
D
Reduced WIP

答案解析

正确答案:C

解析:

The time it takes to setup a product has a direct cost that is a component of the overall cost of producing the item. Not only is the cost of setup reduced, but also the lot size produced can be reduced along with the queue and lead times. When the setup time is reduced, it will immediately reduce the overall cost of the products;