3,028
单选题

Since capacity has already been validated at the MPS level, why is it checked again at the MRP level?

A
Capacity may have changed at the various key work centers
B
Load may have changed at the various key work centers
C
MPS uses only key work centers
D
MRP performs a more detailed capacity check at the work center level

答案解析

正确答案:D

解析:

CRP is a more detailed process than RCCP, master production scheduling doesn't check key work center, but RCCP does;
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

There are multiple strategies in terms of planning capacity to ensure the capability of producing the planned production. One strategy is to employ a capacity cushion in which the available capacity is more than the needed capacity to meet the plan. The negative aspect of maintaining a capacity cushion is that it reduces:

单选题

Of the various capacity planning methods available for high level planning, which would be considered the simplest to establish and use?

单选题

To use a resource profile to generate rough-cut capacity plans, all of the following data is necessary EXCEPT:

单选题

Which of the following is used in conjunction with time phased MRP records and shop floor system records to calculate the capacity needed to produce both open shop orders and planned orders?

单选题

A listing of the required capacity and key resources needed to manufacture one unit of a selected item or family is best defined as:

单选题

When there are make-to-order and make-to-stock parts being manufactured using a single set of plant and equipment, it is known as:

单选题

Advanced planning and scheduling systems determine the optimal schedule by eliminating:

单选题

A process train is a representation of the flow of materials through a process industry manufacturing system. Within this process train, equipment that performs a basic manufacturing step, such as mixing or packaging is called a:

单选题

In a flow factory, the capacity of a work cell would be established by:

单选题

In order for manufacturing planning systems to work properly, lead times in the system must be dependable. This means that queues must be under control. There are three reasons why queues are out of control. Which of the following is NOT a reason for out of control queues?

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码