相关题目
Significant reductions in which of the following lead times has the most positive impact on material planning?
The plan for the production and purchase of components used in making items in the MPS is the
Period 1 2 3 4 5 6 7 8
Gross requirements 22 28 0 20 0 32 22 24
Scheduled receipts 0 40
Projected available 24
lead time=1 week
Order policy: lot for lot
what is the planned order release in period 5?
A component has 3 qualified suppliers, but none has been designated as the primary supplier, which of the following lead times should be used for MRP in order to ensure delivery reliability?
In an ETO environment, what determines the latest point at which the BOM can be completed and released to MRP?
The primary purpose of the BOM in the MRP process is
Pegging is used to
Which of the following features are characteristic of continuous process manufacturing?
1. Low-cost production
2. Multipurpose process technology
3. Price as an order-winning criterion
4. Narrow product range
A company makes products with multiple options and is experiencing a temporary increase in sales, which of the following inventories should be in store?
MRP has calculated a gross demand of 50 units in period 4. The net requirement and safety stock are 0. The order quantity is 100 units, if the next net demand is 20 units in period 6.