A production plan is based on producing the same qty per day. The current month is 20 days and the production plan calls for 8000units. There are 4 models with the following demand. A-3200, B-2400, C-1600, D-800. The sequence for the mixed-model schedule is A-B-C-A-B-D-A-B-C-A. The weekly MPS is:
答案解析
相关题目
A reduction in the lead time results from which of the following actions?
Obtaining processing inspection and testing data is an example of which of the following quality-related costs?
Scheduling to less-than-full capacity facilitates which of the following outcomes?
Which of the following statements about high-volume repetitive manufacturing is true?
Proper workplace organization calls for which of the following actions?
Which of the following basic layout principles should be applied to improve work flow?
Objectives of implementing a work cell include which of the following outcomes?
The following problems were reported from the field:
The primary value of a process map is to show:
Throughput for a family of parts can be increased by use of which of the following approaches?