OH Demand Time Fence Planning time fence
Period 1 2 3 4 5 6 7 8
Forecast 20 20 20 20 20 20 20 20
Customer orders 19 20 21 21 25 24 20 18
PAB 15
Safety stock = 10
Lot size = 30
Using the information provided, which periods would have a master schedule quantity?
A company makes 4 production lines with a variety of features and options offered for each product line. Which of the following tools is most appropriately used to document the product configurations to be built over the next 2 weeks in this situation?
What is the relationship between the number of week in the backlog and the number of weeks within the MPS time fence?
A production plan is based on producing the same qty per day. The current month is 20 days and the production plan calls for 8000units. There are 4 models with the following demand. A-3200, B-2400, C-1600, D-800. The sequence for the mixed-model schedule is A-B-C-A-B-D-A-B-C-A. The weekly MPS is:
Mass customization is the ability to
A company produces MTO product families that use common work centers configured in a functional layout. Ship date are specified by the customer. It is a stable product line in the maturity stage, but demand is erratic. The master scheduler has ongoing problems maintaining a balanced schedule due to randomly appearing overload conditions among the various work centers. A likely cause of the overload condition is
An ATO environment using a mixed model production schedule has a bottleneck work center. The best RCCP approach for determining the feasibility of the MPS is to
A company produces desk clocks as a product family w/20 different end-items. The overall production plan has been set at 8000units a month. Which of the following actions should be master scheduler take to develop the MPS?
A problem with evaluating master scheduling and purchasing performance as they relate to each other is
A data element that can cause the most occurrences of inaccuracy in a master schedule for a particular product is