Which of the following methodologies would be the most appropriately used during the design of a new product to ensure that it meets the customer needs?

A
ESI-Early supplier involvement
B
QFD
C
Concurrent engineering
D
Quality at the source

答案解析

正确答案:B
题目纠错
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

WORK CENTER 210 (in standard hours)
Period    1     2     3     4     5  
PLANNED INPUT  150   150    150    150   150  
ACTUAL INPUT 150 145 130
Period     1     2     3     4     5  
PLANNED OUTPUT 180    180    180    180    150  
ACTUAL OUTPUT 185 140 160
Based on the input/output control chart above, what should the input be in Period 4 in order to reduce the backlog?

单选题

A major effort in JIT is reducing or eliminating the queues. The benefits of reducing the queues are:
I. Faster setup times
II. Reduced inventory investment
III. Shorter lead times

单选题

Setup time reduction in a JIT implementation is very important because:
I. Small lot sizes reduce inventory
II. Production output will increase
III. All of the products can be made constant

单选题

The most important initial qualification for a supplier to possess in order to supply a Just-in-Time manufacturer is:

单选题

Which of the following are benefits of SMED (Single Minute Exchange of Die)?
I. Lower die costs
II. Lower inventory
III. Greater flexibility in manufacturing

单选题

In considering a carrier for use in a JIT delivery system, which of the following are important?
I. Equipment size and type
II. Capability to communicate effectively with supplier and customer
III. Flexibility to schedule changes

单选题

The phrase "one less at a time" refers to which of the following?

单选题

Managing the shop floor more effectively can improve customer service in which of the following ways?
I. Replenishing stock orders on time
II. Improving parts availability
III. Improving inventory accuracy

单选题

Which of the following are valid methods of relieving inventory?
I. Post-deduction transaction
II. Pre-deduct transaction
III. Direct-deduct transaction

单选题

When a set-up procedure occurs while a machine is not operating, it is called:

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码