MRP indicates that SS will be dipped into period 2. The next orders will be received in period 3 due to a common availability issue at the supplier, which of the following actions will most likely occur?

A
No action message from MRP, buyer attempts to expedite order from supplier
B
Action message to reschedule order from period 3 to 2, planner temporarily reduces the SS quantity;
C
No action message generated by MRP so no action from planner
D
Action message to reschedule order from period 3 to 2, planner allows SS to be used

答案解析

正确答案:D

解析:

Any action message will be generated to reschedule the order, however, as the order cannot be expedited, safety stock should be consumed, SS is in place for this very purpose;
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码