A component is defined on only one BOM at level 6, but also has independent demand. Which of the following statements is true?
Period 1 2 3 4 5 6 7 8
Gross requirements 40 10 30 50 50 20 30 40
Scheduled receipts
Projected available 130
order quantity: 40
Safety stock: 10
Lead time: 3 periods
When must a planned order be released to meet a net requirement in period 5?
Which of the following statements applies to the lot-for-lot batch sizing rule?
For the purpose of MRP, it is most important for the BOM to
Which of the following is the most necessary components of an efficient backflushing system?
Pre-requisites for a MRP system include
Period 1 2 3 4 5 6 7 8
Gross requirements 40 40 50 60 60 80 80 80
Scheduled receipts 100
Projected available 60
order quantity: fixed order quantity of 100
Safety stock: 20
Lead time: 2 weeks
Using the information provided, planned orders would be generated with release dates falling in which of the following periods?
Period 1 2 3 4 5 6 7 8
Gross requirements 36 42 50 45 55 55 55 55
Scheduled receipts
Projected available 80
order quantity: fixed order quantity of 100
Safety stock: 10
Lead time: 1 week
What are the PAB in period 4?
MRP indicates that SS will be dipped into period 2. The next orders will be received in period 3 due to a common availability issue at the supplier, which of the following actions will most likely occur?
A parent item has a net demand of 100 units in period 6. Its lead time is two periods. One of the components is used in quantities of 4 per unit, has 0 inventory and a lead time of a week. It is purchased in 1000 units order quantities, which of the following planned order receipts would be the result of the explosion process for the components?