The table provided is an example of which of the following production strategies?
Open inventory=10
Period 1 2 3 4
Inventory 10 10 10 10
Planned production 20 25 30 35
Sales 20 25 30 35

A
balanced
B
hybrid
C
level
D
chase

答案解析

正确答案:D
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

Which of the following actions is part of the pre-sales and operations planning meeting?

单选题

A Canadian-based company has a long-term contract with a US-based supplier. The Canadian company has been experiencing short shipments and variations of the supply lead time with the US supplier for a few months. Which of the following is the most
appropriate action for the master production scheduler in this situation?

单选题

Distribution requirements planning would most directly interface with:

单选题

The question below is based on the following production environment information: In which facility would product unit costs most likely be reduced through a setup reduction program?
Facility A Facility B Facility C Facility D
Product volume High High Lower Lower
Product variety High Lower High Lower
Production LT Long Short Long Short
Operation/product Many Few Many Few
Production resources Many Many Few Few

单选题

The question below is based on the following distribution requirements plan: Lead time is 1 week, lot size is 30, and safety stock is 0. Planned order releases would occur in which of
the following sequences?
Period 1 2 3 4 5 6
Gross requirements 20 15 18 23 26 27
Scheduled receipt 30
PAB 12

单选题

The following question is based on the following information: The master production schedule quantity that should be placed in Period 7 is:
Lead time=0 Lot size=20
DTF=0 PDF=4
On hand=10 SS=3
Period 1 2 3 4 5 6 7 8 9
Forecast 10 10 15 10 10 5 10 10 15
Customer PO 5 2 1
MPS 20 20 20

单选题

The following question is based on the following information: In Period 1, the quantity that would be exploded to component parts is:
Lead time=0 Lot size=20
DTF=0 PDF=4
On hand=10 SS=3
Period 1 2 3 4 5 6 7 8 9
Forecast 10 10 15 10 10 5 10 10 15
Customer PO 5 2 1
MPS 20 20 20

单选题

Key linkages managed by distribution requirements planning within the supply chain include links to:

单选题

From a management perspective, the choice of transportation mode and routing primarily
will affect the:

单选题

The question below is based on the following information: A company has chosen to execute a level production plan. What is the production rate per period?
Beginning inventory: 8 units
Desired ending inventory: 0 unit
Inventory carrying cost: $5/unit/period
Stockout cost: $25/unit/period

Period 1 2 3 4 5
Forecast 100 125 120 95

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码