The following question is based on the following information: In Period 1, the quantity that would be exploded to component parts is:
Lead time=0 Lot size=20
DTF=0 PDF=4
On hand=10 SS=3
Period 1 2 3 4 5 6 7 8 9
Forecast 10 10 15 10 10 5 10 10 15
Customer PO 5 2 1
MPS 20 20 20
答案解析
相关题目
The focus of the sales and operations planning meeting is
Which of the following statement is most correct regarding the production plan in a MTS environment?
A bill of resources is defined as
An objective of the production planning process is to
A company uses a level production strategy to build inventory prior to a peak season, which of the following inventory turns should be expected?
A company produces 10 families of products that require 6 weeks cumulative lead time to produce and are stocked for sale from the distribution center. Which of the following reviews is of little or no value in the sales and operations planning process?
The table provided is an example of which of the following production strategies?
Open inventory=10
Period 1 2 3 4
Inventory 10 10 10 10
Planned production 20 25 30 35
Sales 20 25 30 35
When assessing a manufacturer's risk and likely points of weakness, a key area that must be analyzed is
Which of the following characteristics of a new product being introduced will most affect choice of a product family for sales and operations planning?
In a MTS environment, which of the following is the best reason for developing a manpower plan as part of the sales and operations planning process?