Which of the following are standard priority systems available to a planner?
I. Critical ratio
II. Profit Ratio
III. Start date priority
IV. Due Date priority
答案解析
解析:
1. Critical ratio
2. Start date priority
3. Due Date priority
Profit ratio is a financial measurement and not a priority system
相关题目
Which production environment most leads to lean principles, yet would not be applicable for the use of Kanban?
In a min-max inventory system, inventory equal to the order point plus a variable order quantity is the
Maintaining physical control of point-of-use is accomplished by
The target inventory level of a periodic review system is
A company is experiencing a change in demand from steady to sporadic. It currently uses EOQ to determine purchase quantities for a key component. Which of the following models should it use in the future?
Storage consideration related to inventory accuracy are most likely to include
Which of the following statements best explains how lean initiatives improve inventory accuracy?
A presentation of the flow of materials that shows equipment and inventories in a process industry is a
A supplier has placed goods at a customer location, but does not receive payment until after the goods are consumed, this is an example of
A company has an historical 2% failure rate at final test. The failed units cannot be reworked. Which of the following information should be used in material planning?