Which of the following could be an alternative way of dealing with capacity shortages?
答案解析
解析:
相关题目
A company has a mandate to meet schedule dates, CRP has identified a capacity overload, and it appears the product will be shipped late. Which of the following actions should be done first?
Which of the following benefits is the best use of a MRP simulation capacity?
An infinite capacity planning report would typically show what type of load profile?
CRP uses infinite rather than finite planning because
Capacity that provides protection from planned and unplanned activities is
Which of the following elements is used by CRP to determine total load on work centers in a job shop environment?
A company pursues a chase production strategy during holiday peaks. Which of the following elements is most likely to cause variability if rated capacity is recalculated on a period-by-period basis for CRP?
Which of the following statements about finite capacity loading are true?
A company has few products but highly variable order quantities, and uses forward scheduling, using standard run hours as a basis for calculating completion dates is beneficial because
In an ATO environment, the execution and control function can help ensure a valid material plan by
