In an ATO environment, the execution and control function can help ensure a valid material plan by

A
Achieving production order on-time start and completion dates
B
Identifying alternate routings if the primary routing is unavailable
C
Providing accurate efficiency and utilization factors for work centers
D
Maintaining bottleneck flexibility through utilization of at least 85%

答案解析

正确答案:A

解析:

In any environment, achieving start and completion dates best supports the material;
CPIM PART2-供应链资格认证考试

扫码进入小程序
随时随地练习

相关题目

单选题

The mission of the purchasing department is to identify and qualify adequate sources of competitively priced supply to manufacture the products required by the marketplace. Many times, this mission includes identifying sources regardless of their location. This is called:

单选题

In today's manufacturing environment of eliminating waste, many companies are eliminating the purchase order because it does not add value for the customer. This is accomplished usually by replacing individual PO's with:

单选题

Providing suppliers with an MRP planning report allows the suppliers to do which of the following?
I. Reduce the cost of raw materials
II. Schedule their plants more efficiently
III. Stabilize their workforce

单选题

Company A's purchasing department has been negotiating with a vendor for product 123. The vendor has suggested the company commit to 20% of the vendor's output over the next six months. This practice is known as:

单选题

A scheduled receipt from a vendor can be best defined as a:

单选题

Which of the following are components of purchasing lead time?
I. Vendor lead time
II. Transportation time
III. Stocking time

单选题

Which of the following are included in ordering costs?
I. Order receipt clerical costs
II. Order preparation costs
III. Set-up costs

单选题

True statements regarding the EOQ (Economic Order Quantity) formula include which of the following?
I. It attempts to balance ordering costs with carrying costs.
II. It is a lot-sizing method.
III. The carrying cost portion is considered a "management policy variable".

单选题

There are occasions when the quality of a product will not meet specifications without rework. When this occurs, the product will go back through some of the same operations and maybe some new ones as well. Which of the following describes the best way to handle the rework, so as to be able to calculate the required capacity including the rework?

单选题

Which of the following could be an alternative way of dealing with capacity shortages?

关闭登录弹窗
专为自学备考人员打造
勾选图标
自助导入本地题库
勾选图标
多种刷题考试模式
勾选图标
本地离线答题搜题
勾选图标
扫码考试方便快捷
勾选图标
海量试题每日更新
波浪装饰图
欢迎登录试题通
可以使用以下方式扫码登陆
APP图标
使用APP登录
微信图标
使用微信登录
试题通小程序二维码
联系电话:
400-660-3606
试题通企业微信二维码