All MRP systems operate as exception systems. They generate messages to tell a planner when an out of limits condition is met. For which of the following conditions would an exception message be generated?
I. Planned orders have reached the lead time for ordering.
II. Scheduled receipts due dates are later than the need date.
III. Standard lead time for an end item will result in a late delivery.
答案解析
解析:
相关题目
In a job shop environment, the technique that results in a short-term planned set of projected completion times for operations and simulated queue levels is
Which of the following routing data do both infinite CRP and finite scheduling use for planning and scheduling
Which of the following reporting points is of use when determining run times?
A work center is consistently overloaded to the point where overtime is required nightly and on weekends. This seems to be a problem for only this work center. The most likely reason is
Before delaying a master schedule item to balance load with capacity in a MTO environment, the planner should first check the
The manufacturing environment best suited for the introduction phase of a product's life cycle is
A company uses rated capacity for capacity requirements planning, which of the following statements is true?
When using capacity planning to validate the material plan, which of the following information is most critical?
A call center operates with 130 customer service representatives, in an 8 hour period. The company receives 8000 calls per day and the average call takes 7 minutes, the utilization of the call center is
The amount of scheduled work ahead of a manufacturing facility expressed in terms of hours of work or units of production is called
