196. Which tool is a column chart that shows the number of resources assigned to a project over
time?

A、 responsibility assignment matrix

B、 resource histogram

C、 RACI charts

D、 organizational breakdown structure

答案:B

项目管理期末复习WJH
61. Which approach to product development is currently used by many organizations so a predictive set of steps is used as an overall means to coordinate more detailed steps that are adaptively managed?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-d7d0-c0f9-29e3bb5dbe01.html
点击查看题目
135. In project schedule management, which is an output of controlling the schedule?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6858-c0f9-29e3bb5dbe01.html
点击查看题目
149. Which is true of dummy activities?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8798-c0f9-29e3bb5dbe00.html
点击查看题目
13. Fast tracking is an example of a tool used in management.
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-7628-c0f9-29e3bb5dbe00.html
点击查看题目
46. In what type of organizational structure do project managers have the least amount of authority?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b890-c0f9-29e3bb5dbe00.html
点击查看题目
116. Which approach for constructing a WBS involves refining the work into greater and greater
levels of detail?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-4530-c0f9-29e3bb5dbe00.html
点击查看题目
199. In the Tuckman model, what occurs as team members have different opinions as to how the
team should operate?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-e558-c0f9-29e3bb5dbe00.html
点击查看题目
87. The project management plan is the output of which project planning process?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-0a98-c0f9-29e3bb5dbe02.html
点击查看题目
107. Creating the WBS is a subprocess associated with which process in project scope management?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-31a8-c0f9-29e3bb5dbe01.html
点击查看题目
160. Which technique is used for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-9b20-c0f9-29e3bb5dbe00.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
项目管理期末复习WJH

196. Which tool is a column chart that shows the number of resources assigned to a project over
time?

A、 responsibility assignment matrix

B、 resource histogram

C、 RACI charts

D、 organizational breakdown structure

答案:B

分享
项目管理期末复习WJH
相关题目
61. Which approach to product development is currently used by many organizations so a predictive set of steps is used as an overall means to coordinate more detailed steps that are adaptively managed?

A.  Adaptive

B.  Hybrid

C.  Predictive

D.  Incremental

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-d7d0-c0f9-29e3bb5dbe01.html
点击查看答案
135. In project schedule management, which is an output of controlling the schedule?

A.  activity duration estimate

B.  project management plan update

C.  activity attribute

D.  milestones list

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6858-c0f9-29e3bb5dbe01.html
点击查看答案
149. Which is true of dummy activities?

A.  They have long durations.

B.  They show logical relationships between activities.

C.  They have a large range of resources.

D.  They have limited time periods.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8798-c0f9-29e3bb5dbe00.html
点击查看答案
13. Fast tracking is an example of a tool used in management.

A.  schedule

B.  quality

C.  communication

D.  risk

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-7628-c0f9-29e3bb5dbe00.html
点击查看答案
46. In what type of organizational structure do project managers have the least amount of authority?

A.  Functional

B.  Project

C.  Matrix

D.  Circular

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b890-c0f9-29e3bb5dbe00.html
点击查看答案
116. Which approach for constructing a WBS involves refining the work into greater and greater
levels of detail?

A.  analogy

B.  bottom-up

C.  top-down

D.  mind mapping

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-4530-c0f9-29e3bb5dbe00.html
点击查看答案
199. In the Tuckman model, what occurs as team members have different opinions as to how the
team should operate?

A.  performing

B.  norming

C.  forming

D.  storming

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-e558-c0f9-29e3bb5dbe00.html
点击查看答案
87. The project management plan is the output of which project planning process?

A.  integration management

B.  quality management

C.  scope management

D.  procurement management

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-0a98-c0f9-29e3bb5dbe02.html
点击查看答案
107. Creating the WBS is a subprocess associated with which process in project scope management?

A.  planning

B.  monitoring and controlling

C.  closing

D.  executing

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-31a8-c0f9-29e3bb5dbe01.html
点击查看答案
160. Which technique is used for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost?

A.  dependency

B.  crashing

C.  critical chain scheduling

D.  feeding buffers

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-9b20-c0f9-29e3bb5dbe00.html
点击查看答案