A. Collecting requirements
B. Defining scope
C. Controlling scope
D. Validating scope
A. conglomeration
B. accumulation
C. Decomposition
D. catalyzation
A. total slack
B. free float
C. Backward pass
D. forward pass
A. Member identity
B. Group emphasis
C. People focus
D. Unit integration
A. Determining how many sprints will compose each release
B. Demonstrating the product during a sprint review meeting
C. Completing tasks each day during sprints
D. Creating sprint backlog
A. executing
B. closing
C. planning
D. monitoring
A. In the early phases of a project life cycle, resource needs are usually lowest.
B. In the later phases of the project life cycle, the level of uncertainty is usually the highest.
C. It is much more expensive to make major changes to a project during the earlier phases
than the latter phases.
D. More resources are usually needed during the initial phases of a project than during the
middle or final phases.
A. Kick-off meetings
B. Impact matrices
C. Requests for quotes
D. Fast tracking
A. schedule management plans
B. define project scope
C. estimate activity resources
D. guide project execution
A. Creating scope
B. Defining scope
C. Controlling scope
D. Validating scope