165. Which is a similarity between scope control and schedule control?

A、 Both are initial processes of project time management.

B、 Both of their primary goals is to define project goals and milestones.

C、 Both are portions of the integrated change control process under project integration
management.

D、 Both of these processes should occur before estimating activity durations.

答案:C

项目管理期末复习WJH
186. According to Thamhain and Wilemon, what is the legitimate hierarchical right to issue orders?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-cde8-c0f9-29e3bb5dbe00.html
点击查看题目
92. What process provides enterprise environmental factors as an output?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1650-c0f9-29e3bb5dbe00.html
点击查看题目
69. Which observation is true of the agile approach to software development?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-e770-c0f9-29e3bb5dbe01.html
点击查看题目
161. Which is a similarity between the crashing and fast tracking?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-9b20-c0f9-29e3bb5dbe01.html
点击查看题目
64. The model uses an approach in which developers work with an evolving prototype, using tools such as computer-aided software engineering, joint requirements planning, and joint
application design to facilitate rapid prototyping and code generation.
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-dfa0-c0f9-29e3bb5dbe00.html
点击查看题目
81. Which planning process is within the Project Scope Management knowledge area?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-02c8-c0f9-29e3bb5dbe00.html
点击查看题目
177. Who is best known for distinguishing between motivational factors and hygiene factors when
considering motivation in work settings?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-ba60-c0f9-29e3bb5dbe01.html
点击查看题目
12. Which tool is most likely to be used in project schedule management?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-7240-c0f9-29e3bb5dbe01.html
点击查看题目
96. Which is true about the agile method?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1e20-c0f9-29e3bb5dbe00.html
点击查看题目
4. Galaxy, a construction company, buys a particular brand of tiles manufactured by Tiles and Floors, an eco-friendly tile manufacturing company. However, Tiles and Floors has declared bankruptcy and closed down. At present, Galaxy is facing a crisis because there are no other manufacturers in the market that supplies eco-friendly tiles. Which constraint is Galaxy currently facing?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-62a0-c0f9-29e3bb5dbe00.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
项目管理期末复习WJH

165. Which is a similarity between scope control and schedule control?

A、 Both are initial processes of project time management.

B、 Both of their primary goals is to define project goals and milestones.

C、 Both are portions of the integrated change control process under project integration
management.

D、 Both of these processes should occur before estimating activity durations.

答案:C

分享
项目管理期末复习WJH
相关题目
186. According to Thamhain and Wilemon, what is the legitimate hierarchical right to issue orders?

A.  authority

B.  achievement

C.  expertise

D.  self-actualization

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-cde8-c0f9-29e3bb5dbe00.html
点击查看答案
92. What process provides enterprise environmental factors as an output?

A.  project integration management

B.  project quality management

C.  project human resource management

D.  project procurement management

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1650-c0f9-29e3bb5dbe00.html
点击查看答案
69. Which observation is true of the agile approach to software development?

A.  In the agile method, requirements and solutions evolve through collaboration.

B.  An agile approach sets scope goals, but leaves time and cost goals flexible.

C.  Agile is a predictive model of software development.

D.  In the agile approach, requirements must be clearly expressed early in the life cycle.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-e770-c0f9-29e3bb5dbe01.html
点击查看答案
161. Which is a similarity between the crashing and fast tracking?

A.  both spread out tasks over a long period of time to ensure the quality of work is maintained

B.  both invariably result in increases in total project costs

C.  both can shorten the time needed to finish a project

D.  both are network diagramming techniques used primarily to predict total project duration

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-9b20-c0f9-29e3bb5dbe01.html
点击查看答案
64. The model uses an approach in which developers work with an evolving prototype, using tools such as computer-aided software engineering, joint requirements planning, and joint
application design to facilitate rapid prototyping and code generation.

A.  prototyping life cycle

B.  waterfall life cycle

C.  RAD life cycle

D.  spiral life cycle

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-dfa0-c0f9-29e3bb5dbe00.html
点击查看答案
81. Which planning process is within the Project Scope Management knowledge area?

A.  Schedule development

B.  Developing a project management plan

C.  Creation of a WBS

D.  Quality planning

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-02c8-c0f9-29e3bb5dbe00.html
点击查看答案
177. Who is best known for distinguishing between motivational factors and hygiene factors when
considering motivation in work settings?

A.  Frederick Herzberg

B.  David McClelland

C.  Abraham Maslow

D.  Douglas McGregor

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-ba60-c0f9-29e3bb5dbe01.html
点击查看答案
12. Which tool is most likely to be used in project schedule management?

A.  Payback analysis

B.  Impact matrices

C.  Gantt charts

D.  Fishbone diagrams

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-7240-c0f9-29e3bb5dbe01.html
点击查看答案
96. Which is true about the agile method?

A.  It is often used when a project team can express the scope early in the product life cycle.

B.  It is used when a project team wants to provide a potentially shippable product earlier
rather than later.

C.  It uses several iterations or deliveries of software instead of waiting until the end of the
project to provide a product.

D.  It is used when project teams want to use the predicative approach to a project.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1e20-c0f9-29e3bb5dbe00.html
点击查看答案
4. Galaxy, a construction company, buys a particular brand of tiles manufactured by Tiles and Floors, an eco-friendly tile manufacturing company. However, Tiles and Floors has declared bankruptcy and closed down. At present, Galaxy is facing a crisis because there are no other manufacturers in the market that supplies eco-friendly tiles. Which constraint is Galaxy currently facing?

A.  Resources

B.  Time

C.  Scope

D.  Cost

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-62a0-c0f9-29e3bb5dbe00.html
点击查看答案