A、 Both are initial processes of project time management.
B、 Both of their primary goals is to define project goals and milestones.
C、 Both are portions of the integrated change control process under project integration
management.
D、 Both of these processes should occur before estimating activity durations.
答案:C
A、 Both are initial processes of project time management.
B、 Both of their primary goals is to define project goals and milestones.
C、 Both are portions of the integrated change control process under project integration
management.
D、 Both of these processes should occur before estimating activity durations.
答案:C
A. authority
B. achievement
C. expertise
D. self-actualization
A. project integration management
B. project quality management
C. project human resource management
D. project procurement management
A. In the agile method, requirements and solutions evolve through collaboration.
B. An agile approach sets scope goals, but leaves time and cost goals flexible.
C. Agile is a predictive model of software development.
D. In the agile approach, requirements must be clearly expressed early in the life cycle.
A. both spread out tasks over a long period of time to ensure the quality of work is maintained
B. both invariably result in increases in total project costs
C. both can shorten the time needed to finish a project
D. both are network diagramming techniques used primarily to predict total project duration
A. prototyping life cycle
B. waterfall life cycle
C. RAD life cycle
D. spiral life cycle
A. Schedule development
B. Developing a project management plan
C. Creation of a WBS
D. Quality planning
A. Frederick Herzberg
B. David McClelland
C. Abraham Maslow
D. Douglas McGregor
A. Payback analysis
B. Impact matrices
C. Gantt charts
D. Fishbone diagrams
A. It is often used when a project team can express the scope early in the product life cycle.
B. It is used when a project team wants to provide a potentially shippable product earlier
rather than later.
C. It uses several iterations or deliveries of software instead of waiting until the end of the
project to provide a product.
D. It is used when project teams want to use the predicative approach to a project.
A. Resources
B. Time
C. Scope
D. Cost