159. Which technique involves doing activities in parallel that one would normally do in sequence?

A、 Critical chain scheduling

B、 Crashing

C、 Fast tracking

D、 PERT analysis

答案:C

项目管理期末复习WJH
180. According to McClelland’s acquired-needs theory, what do people who desire harmonious
relationships with other people and need to feel accepted by others have a high need for?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-c230-c0f9-29e3bb5dbe00.html
点击查看题目
1. Which characteristic highlights a difference between projects and operations?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-5ad0-c0f9-29e3bb5dbe00.html
点击查看题目
195. What is the first step in the framework for defining and assigning work?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-dd88-c0f9-29e3bb5dbe00.html
点击查看题目
182. Which test presents subjects with a series of ambiguous pictures and asks them to develop a
spontaneous story for each picture, assuming they will project their own needs into the story?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-c618-c0f9-29e3bb5dbe00.html
点击查看题目
45. In what type of organizational structure do project managers have the most authority?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b4a8-c0f9-29e3bb5dbe01.html
点击查看题目
153. Which provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8f68-c0f9-29e3bb5dbe00.html
点击查看题目
125. Which process involves developing a working replica of the system or some aspect of the
system?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-54d0-c0f9-29e3bb5dbe01.html
点击查看题目
197. Which term refers to the amount of individual resources an existing schedule requires during
specific time periods?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-e170-c0f9-29e3bb5dbe00.html
点击查看题目
36. Which problem-solving approach requires defining the scope of a system, dividing it into its
components, and then identifying and evaluating its problems, opportunities, constraints, and needs?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-a120-c0f9-29e3bb5dbe01.html
点击查看题目
190. Which type of power is based on an individual’s personal charisma?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d5b8-c0f9-29e3bb5dbe00.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
项目管理期末复习WJH

159. Which technique involves doing activities in parallel that one would normally do in sequence?

A、 Critical chain scheduling

B、 Crashing

C、 Fast tracking

D、 PERT analysis

答案:C

分享
项目管理期末复习WJH
相关题目
180. According to McClelland’s acquired-needs theory, what do people who desire harmonious
relationships with other people and need to feel accepted by others have a high need for?

A.  affiliation

B.  self-actualization

C.  power

D.  achievement

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-c230-c0f9-29e3bb5dbe00.html
点击查看答案
1. Which characteristic highlights a difference between projects and operations?

A.  Projects are undertaken to sustain an organization’s business whereas operations are not.

B.  Operations are undertaken to create unique products, services, or results whereas projects
are not.

C.  Projects are temporary endeavors whereas an organization’s operations are ongoing in
nature.

D.  Operations have well-defined objectives whereas projects do not need to have a unique
purpose.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-5ad0-c0f9-29e3bb5dbe00.html
点击查看答案
195. What is the first step in the framework for defining and assigning work?

A.  defining how the work will be accomplished

B.  breaking down the work into manageable elements

C.  finalizing the project requirements

D.  assigning work responsibilities

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-dd88-c0f9-29e3bb5dbe00.html
点击查看答案
182. Which test presents subjects with a series of ambiguous pictures and asks them to develop a
spontaneous story for each picture, assuming they will project their own needs into the story?

A.  RAM

B.  MBTI

C.  TAT

D.  RACI

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-c618-c0f9-29e3bb5dbe00.html
点击查看答案
45. In what type of organizational structure do project managers have the most authority?

A.  Functional

B.  Project

C.  Matrix

D.  Circular

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b4a8-c0f9-29e3bb5dbe01.html
点击查看答案
153. Which provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format?

A.  Gantt charts

B.  Critical path analysis

C.  Arrow diagramming method

D.  PERT analysis

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8f68-c0f9-29e3bb5dbe00.html
点击查看答案
125. Which process involves developing a working replica of the system or some aspect of the
system?

A.  Prototyping

B.  Variance

C.  Decomposition

D.  Use case modeling

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-54d0-c0f9-29e3bb5dbe01.html
点击查看答案
197. Which term refers to the amount of individual resources an existing schedule requires during
specific time periods?

A.  resource loading

B.  resource leveling

C.  resource histogram

D.  resource logs

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-e170-c0f9-29e3bb5dbe00.html
点击查看答案
36. Which problem-solving approach requires defining the scope of a system, dividing it into its
components, and then identifying and evaluating its problems, opportunities, constraints, and needs?

A.  Linear programming

B.  Independent component analysis

C.  Principal component analysis

D.  Systems analysis

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-a120-c0f9-29e3bb5dbe01.html
点击查看答案
190. Which type of power is based on an individual’s personal charisma?

A.  legitimate

B.  coercive

C.  reward

D.  referent

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d5b8-c0f9-29e3bb5dbe00.html