152. In project schedule management, the ultimate goal of which process is to provide a basis for
monitoring project progress for the time dimension of the project?

A、 defining activities

B、 sequencing activities

C、 developing a schedule

D、 estimating activity resources

答案:C

试题通
项目管理期末复习WJH
试题通
175. What is at the top of Maslow’s hierarchy of needs?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-b678-c0f9-29e3bb5dbe01.html
点击查看题目
3. The role of a is to provide direction and funding for a project.
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-5eb8-c0f9-29e3bb5dbe01.html
点击查看题目
197. Which term refers to the amount of individual resources an existing schedule requires during
specific time periods?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-e170-c0f9-29e3bb5dbe00.html
点击查看题目
16. Team building exercises and motivation techniques are tools used in management.
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-7a10-c0f9-29e3bb5dbe01.html
点击查看题目
112. What is the main technique used in creating a WBS, which involves subdividing project
deliverables into smaller pieces?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-3d60-c0f9-29e3bb5dbe00.html
点击查看题目
142. Which dependencies are sometimes referred to as soft logic and should be used with care
because they may limit later scheduling options?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-77f8-c0f9-29e3bb5dbe00.html
点击查看题目
127. Which process uses highly organized and intensive workshops to bring together project
stakeholders—the sponsor, users, business analysts, programmers, and so on—to jointly define and design information systems?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-58b8-c0f9-29e3bb5dbe01.html
点击查看题目
84. Which is an example of a pre-initiation task?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-06b0-c0f9-29e3bb5dbe01.html
点击查看题目
52. In organizational culture, what does people focus refer to?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-c448-c0f9-29e3bb5dbe00.html
点击查看题目
198. Which technique is used for resolving resource conflicts by delaying tasks?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-e170-c0f9-29e3bb5dbe01.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
试题通
项目管理期末复习WJH

152. In project schedule management, the ultimate goal of which process is to provide a basis for
monitoring project progress for the time dimension of the project?

A、 defining activities

B、 sequencing activities

C、 developing a schedule

D、 estimating activity resources

答案:C

试题通
分享
试题通
试题通
项目管理期末复习WJH
相关题目
175. What is at the top of Maslow’s hierarchy of needs?

A.  esteem

B.  self-actualization

C.  physiological

D.  social

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-b678-c0f9-29e3bb5dbe01.html
点击查看答案
3. The role of a is to provide direction and funding for a project.

A.  project sponsor

B.  project manager

C.  support staff member

D.  project team

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-5eb8-c0f9-29e3bb5dbe01.html
点击查看答案
197. Which term refers to the amount of individual resources an existing schedule requires during
specific time periods?

A.  resource loading

B.  resource leveling

C.  resource histogram

D.  resource logs

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-e170-c0f9-29e3bb5dbe00.html
点击查看答案
16. Team building exercises and motivation techniques are tools used in management.

A.  procurement

B.  scope

C.  resource

D.  cost

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-7a10-c0f9-29e3bb5dbe01.html
点击查看答案
112. What is the main technique used in creating a WBS, which involves subdividing project
deliverables into smaller pieces?

A.  conglomeration

B.  accumulation

C.  Decomposition

D.  catalyzation

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-3d60-c0f9-29e3bb5dbe00.html
点击查看答案
142. Which dependencies are sometimes referred to as soft logic and should be used with care
because they may limit later scheduling options?

A.  mandatory

B.  discretionary

C.  external

D.  inherent

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-77f8-c0f9-29e3bb5dbe00.html
点击查看答案
127. Which process uses highly organized and intensive workshops to bring together project
stakeholders—the sponsor, users, business analysts, programmers, and so on—to jointly define and design information systems?

A.  Prototyping

B.  JAD

C.  RAD

D.  Use case modeling

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-58b8-c0f9-29e3bb5dbe01.html
点击查看答案
84. Which is an example of a pre-initiation task?

A.  Drawing up a work breakdown structure

B.  Developing a business case for a project

C.  Drafting the project charter

D.  Identifying stakeholders

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-06b0-c0f9-29e3bb5dbe01.html
点击查看答案
52. In organizational culture, what does people focus refer to?

A.  The degree to which the organization monitors and responds to changes in the external
environment

B.  The degree to which rules, policies, and direct supervision are used to oversee and control
employee behavior

C.  The degree to which management’s decisions take into account the effect of outcomes on
employees within the organization

D.  The degree to which employees are encouraged to be aggressive, innovative, and risk
seeking

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-c448-c0f9-29e3bb5dbe00.html
点击查看答案
198. Which technique is used for resolving resource conflicts by delaying tasks?

A.  resource loading

B.  resource leveling

C.  resource allocation

D.  resource histogram

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-e170-c0f9-29e3bb5dbe01.html
点击查看答案
试题通小程序
试题通app下载