单选题
)
131. In project schedule management, which process primarily involve identifying and documenting the relationships between project activities?

A、 defining activities

B、 sequencing activities

C、 planning schedule management

D、 estimating activity durations

答案:B

试题通
项目管理期末复习WJH
试题通
120. Mind mapping can be used for developing WBSs using which approach?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-4d00-c0f9-29e3bb5dbe00.html
点击查看题目
189. Which type of power involves using incentives to induce people to do things?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d1d0-c0f9-29e3bb5dbe01.html
点击查看题目
150. Which is one of the main outputs of estimating activity resources process?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8798-c0f9-29e3bb5dbe01.html
点击查看题目
42. In Rizzati Corp, vice presidents in departments such as engineering, manufacturing, IT, and
human resources report directly to the chief executive officer and undertake their tasks
independently of each other. The staffs of these departments have specialized skills in their
respective disciplines. Which type of organizational structure does Rizatti Corp have?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b0c0-c0f9-29e3bb5dbe00.html
点击查看题目
98. Which activity is a part of the Scrum planning process?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-2208-c0f9-29e3bb5dbe00.html
点击查看题目
188. Which type of power involves using punishment, threats, or other negative approaches to get
people to do things they do not want to do?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d1d0-c0f9-29e3bb5dbe00.html
点击查看题目
178. According to Herzberg, which is a motivational factor?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-be48-c0f9-29e3bb5dbe00.html
点击查看题目
134. In project schedule management, which process primarily involves checking and managing
changes to the project schedule?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6858-c0f9-29e3bb5dbe00.html
点击查看题目
140. In project schedule management, what is the next step after defining project activities?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-7410-c0f9-29e3bb5dbe00.html
点击查看题目
187. According to Thamhain and Wilemon, what is the ability to improve a worker’s position?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-cde8-c0f9-29e3bb5dbe01.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
试题通
项目管理期末复习WJH

131. In project schedule management, which process primarily involve identifying and documenting the relationships between project activities?

A、 defining activities

B、 sequencing activities

C、 planning schedule management

D、 estimating activity durations

答案:B

试题通
分享
试题通
试题通
项目管理期末复习WJH
相关题目
120. Mind mapping can be used for developing WBSs using which approach?

A.  analogy approach only

B.  bottom-up or analogy approach

C.  top-down or bottom-up approach

D.  any approach

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-4d00-c0f9-29e3bb5dbe00.html
点击查看答案
189. Which type of power involves using incentives to induce people to do things?

A.  legitimate

B.  coercive

C.  reward

D.  referent

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d1d0-c0f9-29e3bb5dbe01.html
点击查看答案
150. Which is one of the main outputs of estimating activity resources process?

A.  project documents update

B.  milestone list

C.  breakdown structure

D.  activity duration estimate

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8798-c0f9-29e3bb5dbe01.html
点击查看答案
42. In Rizzati Corp, vice presidents in departments such as engineering, manufacturing, IT, and
human resources report directly to the chief executive officer and undertake their tasks
independently of each other. The staffs of these departments have specialized skills in their
respective disciplines. Which type of organizational structure does Rizatti Corp have?

A.  Project

B.  Symbolic

C.  Matrix

D.  Functional

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b0c0-c0f9-29e3bb5dbe00.html
点击查看答案
98. Which activity is a part of the Scrum planning process?

A.  Determining how many sprints will compose each release

B.  Demonstrating the product during a sprint review meeting

C.  Completing tasks each day during sprints

D.  Creating sprint backlog

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-2208-c0f9-29e3bb5dbe00.html
点击查看答案
188. Which type of power involves using punishment, threats, or other negative approaches to get
people to do things they do not want to do?

A.  legitimate

B.  coercive

C.  reward

D.  referent

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d1d0-c0f9-29e3bb5dbe00.html
点击查看答案
178. According to Herzberg, which is a motivational factor?

A.  recognition

B.  salary

C.  training

D.  health benefits

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-be48-c0f9-29e3bb5dbe00.html
点击查看答案
134. In project schedule management, which process primarily involves checking and managing
changes to the project schedule?

A.  estimating activity durations

B.  developing the schedule

C.  controlling the schedule

D.  estimating activity resources

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6858-c0f9-29e3bb5dbe00.html
点击查看答案
140. In project schedule management, what is the next step after defining project activities?

A.  planning schedule management

B.  determining their dependencies

C.  controlling the schedule

D.  estimating activity duration

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-7410-c0f9-29e3bb5dbe00.html
点击查看答案
187. According to Thamhain and Wilemon, what is the ability to improve a worker’s position?

A.  penalty

B.  assignment

C.  expertise

D.  promotion

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-cde8-c0f9-29e3bb5dbe01.html
点击查看答案