题目内容
(
单选题
)
130. In project schedule management, which process generates the main outputs of an activity list,
activity attributes, and a milestone list?

A、 sequencing activities

B、 defining activities

C、 resource estimating activities

D、 estimating activity durations

答案:B

试题通
项目管理期末复习WJH
试题通
56. Select an example of external stakeholders for an organization.
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-d000-c0f9-29e3bb5dbe00.html
点击查看题目
175. What is at the top of Maslow’s hierarchy of needs?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-b678-c0f9-29e3bb5dbe01.html
点击查看题目
183. Who is best known for developing Theory X and Theory Y?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-c618-c0f9-29e3bb5dbe01.html
点击查看题目
111. Which document contains a deliverable-oriented grouping of the work involved in a project
that defines the total scope of the project?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-3978-c0f9-29e3bb5dbe01.html
点击查看题目
33. Enterprise project management software is also known as a tool of project management
software.
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-9950-c0f9-29e3bb5dbe02.html
点击查看题目
47. Which of the following is true of a matrix organizational structure?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b890-c0f9-29e3bb5dbe01.html
点击查看题目
131. In project schedule management, which process primarily involve identifying and documenting the relationships between project activities?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6088-c0f9-29e3bb5dbe01.html
点击查看题目
90. What tool provides a basis for creating the project schedule and performing earned value
management for measuring and forecasting project performance?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1268-c0f9-29e3bb5dbe00.html
点击查看题目
169. The main outputs of which process are team performance assessments, change requests, and
updates to several documents?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-aac0-c0f9-29e3bb5dbe01.html
点击查看题目
6. Which knowledge area involves defining and managing all the work required to complete the
project successfully?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-6688-c0f9-29e3bb5dbe00.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
试题通
项目管理期末复习WJH

130. In project schedule management, which process generates the main outputs of an activity list,
activity attributes, and a milestone list?

A、 sequencing activities

B、 defining activities

C、 resource estimating activities

D、 estimating activity durations

答案:B

试题通
分享
试题通
试题通
项目管理期末复习WJH
相关题目
56. Select an example of external stakeholders for an organization.

A.  Top managers

B.  Functional managers

C.  Employees

D.  Competitors

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-d000-c0f9-29e3bb5dbe00.html
点击查看答案
175. What is at the top of Maslow’s hierarchy of needs?

A.  esteem

B.  self-actualization

C.  physiological

D.  social

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-b678-c0f9-29e3bb5dbe01.html
点击查看答案
183. Who is best known for developing Theory X and Theory Y?

A.  Frederick Herzberg

B.  David McClelland

C.  Abraham Maslow

D.  Douglas McGregor

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-c618-c0f9-29e3bb5dbe01.html
点击查看答案
111. Which document contains a deliverable-oriented grouping of the work involved in a project
that defines the total scope of the project?

A.  project charter

B.  business case

C.  project scope statement

D.  work breakdown structure

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-3978-c0f9-29e3bb5dbe01.html
点击查看答案
33. Enterprise project management software is also known as a tool of project management
software.

A.  baseline

B.  midrange

C.  low-end

D.  high-end

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-9950-c0f9-29e3bb5dbe02.html
点击查看答案
47. Which of the following is true of a matrix organizational structure?

A.  In a matrix organizational structure, employees are organized into departments according
to their skills, and there is little interaction between employees from different departments.

B.  Project managers in matrix organizations have staff from only a single functional area
working on their projects.

C.  In a strong matrix organizational structure, the project manager controls the project budget
and has moderate to high authority.

D.  A matrix organizational structure is hierarchical, but instead of functional managers
reporting to the CEO, program managers report to the CEO.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b890-c0f9-29e3bb5dbe01.html
点击查看答案
131. In project schedule management, which process primarily involve identifying and documenting the relationships between project activities?

A.  defining activities

B.  sequencing activities

C.  planning schedule management

D.  estimating activity durations

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6088-c0f9-29e3bb5dbe01.html
点击查看答案
90. What tool provides a basis for creating the project schedule and performing earned value
management for measuring and forecasting project performance?

A.  scope statement

B.  cost management plan

C.  work breakdown structure

D.  project charter

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1268-c0f9-29e3bb5dbe00.html
点击查看答案
169. The main outputs of which process are team performance assessments, change requests, and
updates to several documents?

A.  managing the project team

B.  acquiring the project team

C.  developing the project team

D.  human resource planning

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-aac0-c0f9-29e3bb5dbe01.html
点击查看答案
6. Which knowledge area involves defining and managing all the work required to complete the
project successfully?

A.  Project resource management

B.  Project scope management

C.  Project time management

D.  Project cost management

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-6688-c0f9-29e3bb5dbe00.html
点击查看答案