单选题
)
111. Which document contains a deliverable-oriented grouping of the work involved in a project
that defines the total scope of the project?

A、 project charter

B、 business case

C、 project scope statement

D、 work breakdown structure

答案:D

试题通
项目管理期末复习WJH
试题通
172. What need is at the highest level in Maslow’s structure?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-b290-c0f9-29e3bb5dbe00.html
点击查看题目
151. After working with key stakeholders to define activities and calculate their resources, what is
the next process in project schedule management?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8798-c0f9-29e3bb5dbe02.html
点击查看题目
69. Which observation is true of the agile approach to software development?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-e770-c0f9-29e3bb5dbe01.html
点击查看题目
147. During which relationship is the “from” activity unable start until the “to” activity is started?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-7fc8-c0f9-29e3bb5dbe01.html
点击查看题目
150. Which is one of the main outputs of estimating activity resources process?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8798-c0f9-29e3bb5dbe01.html
点击查看题目
193. Which concept refers to matching certain behaviors of the other person?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d9a0-c0f9-29e3bb5dbe00.html
点击查看题目
1. Which characteristic highlights a difference between projects and operations?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-5ad0-c0f9-29e3bb5dbe00.html
点击查看题目
95. An organizational process assets update is the output of which closing process?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1a38-c0f9-29e3bb5dbe01.html
点击查看题目
105. Which action involves reviewing the project charter, requirements documents, and
organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-2dc0-c0f9-29e3bb5dbe01.html
点击查看题目
144. In an AOA network diagram, what occurs when two or more activities follow a single node?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-7be0-c0f9-29e3bb5dbe00.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
试题通
项目管理期末复习WJH

111. Which document contains a deliverable-oriented grouping of the work involved in a project
that defines the total scope of the project?

A、 project charter

B、 business case

C、 project scope statement

D、 work breakdown structure

答案:D

试题通
分享
试题通
试题通
项目管理期末复习WJH
相关题目
172. What need is at the highest level in Maslow’s structure?

A.  deficiency

B.  growth

C.  safety

D.  physiological

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-b290-c0f9-29e3bb5dbe00.html
点击查看答案
151. After working with key stakeholders to define activities and calculate their resources, what is
the next process in project schedule management?

A.  develop the schedule.

B.  control the schedule.

C.  determine their dependencies.

D.  estimate the duration of activities.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8798-c0f9-29e3bb5dbe02.html
点击查看答案
69. Which observation is true of the agile approach to software development?

A.  In the agile method, requirements and solutions evolve through collaboration.

B.  An agile approach sets scope goals, but leaves time and cost goals flexible.

C.  Agile is a predictive model of software development.

D.  In the agile approach, requirements must be clearly expressed early in the life cycle.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-e770-c0f9-29e3bb5dbe01.html
点击查看答案
147. During which relationship is the “from” activity unable start until the “to” activity is started?

A.  start-to-start

B.  finish-to-finish

C.  finish-to-start

D.  start-to-finish

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-7fc8-c0f9-29e3bb5dbe01.html
点击查看答案
150. Which is one of the main outputs of estimating activity resources process?

A.  project documents update

B.  milestone list

C.  breakdown structure

D.  activity duration estimate

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8798-c0f9-29e3bb5dbe01.html
点击查看答案
193. Which concept refers to matching certain behaviors of the other person?

A.  empathic listening

B.  rapport

C.  synergy

D.  mirroring

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d9a0-c0f9-29e3bb5dbe00.html
点击查看答案
1. Which characteristic highlights a difference between projects and operations?

A.  Projects are undertaken to sustain an organization’s business whereas operations are not.

B.  Operations are undertaken to create unique products, services, or results whereas projects
are not.

C.  Projects are temporary endeavors whereas an organization’s operations are ongoing in
nature.

D.  Operations have well-defined objectives whereas projects do not need to have a unique
purpose.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-5ad0-c0f9-29e3bb5dbe00.html
点击查看答案
95. An organizational process assets update is the output of which closing process?

A.  project integration management

B.  project quality management

C.  project procurement management

D.  project time management

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1a38-c0f9-29e3bb5dbe01.html
点击查看答案
105. Which action involves reviewing the project charter, requirements documents, and
organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved?

A.  Creating scope

B.  Defining scope

C.  Controlling scope

D.  Validating scope

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-2dc0-c0f9-29e3bb5dbe01.html
点击查看答案
144. In an AOA network diagram, what occurs when two or more activities follow a single node?

A.  combinations

B.  buffers

C.  mergers

D.  bursts

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-7be0-c0f9-29e3bb5dbe00.html