单选题
)
108. Which output documents how project needs will be analyzed, documented, and managed?

A、 requirements traceability matrix

B、 requirements management plan

C、 WBS

D、 project scope statement

答案:B

项目管理期末复习WJH
35. Projects must operate in a broad organizational environment, and project managers need to
consider projects within the greater organizational context. Which approach describes the holistic
view of carrying out projects within the context of the organization?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-a120-c0f9-29e3bb5dbe00.html
点击查看题目
8. Which project management knowledge area primarily involves generating, collecting,
disseminating, and storing project information?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-6a70-c0f9-29e3bb5dbe01.html
点击查看题目
56. Select an example of external stakeholders for an organization.
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-d000-c0f9-29e3bb5dbe00.html
点击查看题目
182. Which test presents subjects with a series of ambiguous pictures and asks them to develop a
spontaneous story for each picture, assuming they will project their own needs into the story?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-c618-c0f9-29e3bb5dbe00.html
点击查看题目
27. A Gantt chart is a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a format.
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-9180-c0f9-29e3bb5dbe00.html
点击查看题目
63. In which systems development life cycle do model developers use a model to generate functional requirements and physical design specifications simultaneously?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-dbb8-c0f9-29e3bb5dbe01.html
点击查看题目
39. The symbolic perspective of an organization:
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-a8f0-c0f9-29e3bb5dbe00.html
点击查看题目
179. What do people who seek to excel and tend to avoid both low-risk and high-risk situations to
improve their chances for achieving something worthwhile have a high need for?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-be48-c0f9-29e3bb5dbe01.html
点击查看题目
97. Which project would be compatible with the use of the agile approach?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1e20-c0f9-29e3bb5dbe01.html
点击查看题目
50. Which characteristic of organizational culture refers to the degree to which employees identify
with the organization as a whole, rather than with their types of job or profession?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-c060-c0f9-29e3bb5dbe00.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
项目管理期末复习WJH

108. Which output documents how project needs will be analyzed, documented, and managed?

A、 requirements traceability matrix

B、 requirements management plan

C、 WBS

D、 project scope statement

答案:B

分享
项目管理期末复习WJH
相关题目
35. Projects must operate in a broad organizational environment, and project managers need to
consider projects within the greater organizational context. Which approach describes the holistic
view of carrying out projects within the context of the organization?

A.  Linear analysis

B.  Systems thinking

C.  Reductionism

D.  The silo approach

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-a120-c0f9-29e3bb5dbe00.html
点击查看答案
8. Which project management knowledge area primarily involves generating, collecting,
disseminating, and storing project information?

A.  Project cost management

B.  Project procurement management

C.  Project time management

D.  Project communications management

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-6a70-c0f9-29e3bb5dbe01.html
点击查看答案
56. Select an example of external stakeholders for an organization.

A.  Top managers

B.  Functional managers

C.  Employees

D.  Competitors

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-d000-c0f9-29e3bb5dbe00.html
点击查看答案
182. Which test presents subjects with a series of ambiguous pictures and asks them to develop a
spontaneous story for each picture, assuming they will project their own needs into the story?

A.  RAM

B.  MBTI

C.  TAT

D.  RACI

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-c618-c0f9-29e3bb5dbe00.html
点击查看答案
27. A Gantt chart is a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a format.

A.  calendar

B.  line graph

C.  bar graph

D.  pie chart

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-9180-c0f9-29e3bb5dbe00.html
点击查看答案
63. In which systems development life cycle do model developers use a model to generate functional requirements and physical design specifications simultaneously?

A.  RAD life cycle

B.  Prototyping life cycle

C.  Spiral life cycle

D.  Waterfall life cycle

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-dbb8-c0f9-29e3bb5dbe01.html
点击查看答案
39. The symbolic perspective of an organization:

A.  focuses on different groups’ roles and responsibilities to meet the goals and policies set
by top management.

B.  views the organization as coalitions composed of varied individuals and interest groups.

C.  focuses on providing harmony between the needs of the organization and the needs of
people.

D.  focuses on the meanings of the culture, language, traditions, and image of the organization.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-a8f0-c0f9-29e3bb5dbe00.html
点击查看答案
179. What do people who seek to excel and tend to avoid both low-risk and high-risk situations to
improve their chances for achieving something worthwhile have a high need for?

A.  affiliation

B.  security

C.  power

D.  achievement

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-be48-c0f9-29e3bb5dbe01.html
点击查看答案
97. Which project would be compatible with the use of the agile approach?

A.  Projects with inexperienced and dispersed teams

B.  Projects that have a fairly rigid completion date

C.  Projects with clear-up front requirements

D.  Projects that have more flexible scheduling

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1e20-c0f9-29e3bb5dbe01.html
点击查看答案
50. Which characteristic of organizational culture refers to the degree to which employees identify
with the organization as a whole, rather than with their types of job or profession?

A.  Member identity

B.  People focus

C.  Group emphasis

D.  Unit integration