题目内容
(
单选题
)
106. Which action involves normalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables?

A、 Creating scope

B、 Defining scope

C、 Controlling scope

D、 Validating scope

答案:D

项目管理期末复习WJH
112. What is the main technique used in creating a WBS, which involves subdividing project
deliverables into smaller pieces?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-3d60-c0f9-29e3bb5dbe00.html
点击查看题目
151. After working with key stakeholders to define activities and calculate their resources, what is
the next process in project schedule management?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8798-c0f9-29e3bb5dbe02.html
点击查看题目
95. An organizational process assets update is the output of which closing process?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1a38-c0f9-29e3bb5dbe01.html
点击查看题目
38. The frame of an organization focuses on providing harmony between the needs of the
organization and the needs of people.
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-a508-c0f9-29e3bb5dbe01.html
点击查看题目
44. In a organizational structure, personnel often report to both a functional manager and one or more project managers.
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b4a8-c0f9-29e3bb5dbe00.html
点击查看题目
191. What term is used for taking time to renew oneself physically, spiritually, mentally and socially?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d5b8-c0f9-29e3bb5dbe01.html
点击查看题目
32. Which type of tool is usually recommended for small projects and single users?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-9950-c0f9-29e3bb5dbe01.html
点击查看题目
72. Which processes include acquiring and developing the project team, performing quality
assurance, distributing information, managing stakeholder expectations, and conducting
procurements?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-ef40-c0f9-29e3bb5dbe00.html
点击查看题目
1. Which characteristic highlights a difference between projects and operations?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-5ad0-c0f9-29e3bb5dbe00.html
点击查看题目
28. A is an organizational group responsible for coordinating the project management
function throughout an organization.
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-9180-c0f9-29e3bb5dbe01.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
项目管理期末复习WJH

106. Which action involves normalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables?

A、 Creating scope

B、 Defining scope

C、 Controlling scope

D、 Validating scope

答案:D

分享
项目管理期末复习WJH
相关题目
112. What is the main technique used in creating a WBS, which involves subdividing project
deliverables into smaller pieces?

A.  conglomeration

B.  accumulation

C.  Decomposition

D.  catalyzation

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-3d60-c0f9-29e3bb5dbe00.html
点击查看答案
151. After working with key stakeholders to define activities and calculate their resources, what is
the next process in project schedule management?

A.  develop the schedule.

B.  control the schedule.

C.  determine their dependencies.

D.  estimate the duration of activities.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8798-c0f9-29e3bb5dbe02.html
点击查看答案
95. An organizational process assets update is the output of which closing process?

A.  project integration management

B.  project quality management

C.  project procurement management

D.  project time management

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1a38-c0f9-29e3bb5dbe01.html
点击查看答案
38. The frame of an organization focuses on providing harmony between the needs of the
organization and the needs of people.

A.  structural

B.  human resources

C.  political

D.  symbolic

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-a508-c0f9-29e3bb5dbe01.html
点击查看答案
44. In a organizational structure, personnel often report to both a functional manager and one or more project managers.

A.  project

B.  symbolic

C.  matrix

D.  functional

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b4a8-c0f9-29e3bb5dbe00.html
点击查看答案
191. What term is used for taking time to renew oneself physically, spiritually, mentally and socially?

A.  empathic mirroring

B.  sharpening the saw

C.  synergizing

D.  thinking win/win

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d5b8-c0f9-29e3bb5dbe01.html
点击查看答案
32. Which type of tool is usually recommended for small projects and single users?

A.  Low-end

B.  Midrange

C.  High-end

D.  Upper range

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-9950-c0f9-29e3bb5dbe01.html
点击查看答案
72. Which processes include acquiring and developing the project team, performing quality
assurance, distributing information, managing stakeholder expectations, and conducting
procurements?

A.  monitoring and controlling

B.  executing

C.  planning

D.  initiating

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-ef40-c0f9-29e3bb5dbe00.html
点击查看答案
1. Which characteristic highlights a difference between projects and operations?

A.  Projects are undertaken to sustain an organization’s business whereas operations are not.

B.  Operations are undertaken to create unique products, services, or results whereas projects
are not.

C.  Projects are temporary endeavors whereas an organization’s operations are ongoing in
nature.

D.  Operations have well-defined objectives whereas projects do not need to have a unique
purpose.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-5ad0-c0f9-29e3bb5dbe00.html
点击查看答案
28. A is an organizational group responsible for coordinating the project management
function throughout an organization.

A.  Project Management Office

B.  Project Management Professional

C.  Project Management Center

D.  Portfolio Group

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-9180-c0f9-29e3bb5dbe01.html