104. Which action involves defining and documenting the features and functions of the products
produced during the project as well as the processes used for creating them?

A、 Collecting requirements

B、 Defining scope

C、 Controlling scope

D、 Validating scope

答案:A

试题通
项目管理期末复习WJH
试题通
130. In project schedule management, which process generates the main outputs of an activity list,
activity attributes, and a milestone list?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6088-c0f9-29e3bb5dbe00.html
点击查看题目
55. In organizational culture, what does control refer to?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-cc18-c0f9-29e3bb5dbe00.html
点击查看题目
129. Which process in project schedule management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-5ca0-c0f9-29e3bb5dbe01.html
点击查看题目
131. In project schedule management, which process primarily involve identifying and documenting the relationships between project activities?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6088-c0f9-29e3bb5dbe01.html
点击查看题目
77. The project scope management knowledge area maps to which process group through the
activities of scope validation and scope control?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-faf8-c0f9-29e3bb5dbe00.html
点击查看题目
47. Which of the following is true of a matrix organizational structure?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b890-c0f9-29e3bb5dbe01.html
点击查看题目
132. In project schedule management, which process involves estimating the number of work
periods that are needed to complete individual activities?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6470-c0f9-29e3bb5dbe00.html
点击查看题目
78. The project schedule management knowledge area maps to which process group through the
activity of schedule control?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-faf8-c0f9-29e3bb5dbe01.html
点击查看题目
158. What is the latest possible time an activity might begin without delaying the project finish date?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-9738-c0f9-29e3bb5dbe01.html
点击查看题目
63. In which systems development life cycle do model developers use a model to generate functional requirements and physical design specifications simultaneously?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-dbb8-c0f9-29e3bb5dbe01.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
试题通
项目管理期末复习WJH

104. Which action involves defining and documenting the features and functions of the products
produced during the project as well as the processes used for creating them?

A、 Collecting requirements

B、 Defining scope

C、 Controlling scope

D、 Validating scope

答案:A

试题通
分享
试题通
试题通
项目管理期末复习WJH
相关题目
130. In project schedule management, which process generates the main outputs of an activity list,
activity attributes, and a milestone list?

A.  sequencing activities

B.  defining activities

C.  resource estimating activities

D.  estimating activity durations

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6088-c0f9-29e3bb5dbe00.html
点击查看答案
55. In organizational culture, what does control refer to?

A.  The degree to which the organization monitors and responds to changes in the external
environment

B.  The degree to which rules, policies, and direct supervision are used to oversee employee
behavior

C.  The degree to which management focuses on outcomes rather than on techniques and
processes used to achieve results

D.  The degree to which employees are encouraged to be aggressive, innovative, and risk
seeking

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-cc18-c0f9-29e3bb5dbe00.html
点击查看答案
129. Which process in project schedule management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables?

A.  defining activities

B.  sequencing activities

C.  developing the schedule

D.  estimating activity durations

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-5ca0-c0f9-29e3bb5dbe01.html
点击查看答案
131. In project schedule management, which process primarily involve identifying and documenting the relationships between project activities?

A.  defining activities

B.  sequencing activities

C.  planning schedule management

D.  estimating activity durations

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6088-c0f9-29e3bb5dbe01.html
点击查看答案
77. The project scope management knowledge area maps to which process group through the
activities of scope validation and scope control?

A.  initiating

B.  planning

C.  Executing

D.  monitoring and controlling

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-faf8-c0f9-29e3bb5dbe00.html
点击查看答案
47. Which of the following is true of a matrix organizational structure?

A.  In a matrix organizational structure, employees are organized into departments according
to their skills, and there is little interaction between employees from different departments.

B.  Project managers in matrix organizations have staff from only a single functional area
working on their projects.

C.  In a strong matrix organizational structure, the project manager controls the project budget
and has moderate to high authority.

D.  A matrix organizational structure is hierarchical, but instead of functional managers
reporting to the CEO, program managers report to the CEO.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b890-c0f9-29e3bb5dbe01.html
点击查看答案
132. In project schedule management, which process involves estimating the number of work
periods that are needed to complete individual activities?

A.  defining activities

B.  sequencing activities

C.  planning schedule management

D.  estimating activity durations

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-6470-c0f9-29e3bb5dbe00.html
点击查看答案
78. The project schedule management knowledge area maps to which process group through the
activity of schedule control?

A.  initiating

B.  planning

C.  Executing

D.  monitoring and controlling

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-faf8-c0f9-29e3bb5dbe01.html
点击查看答案
158. What is the latest possible time an activity might begin without delaying the project finish date?

A.  early finish date

B.  late finish date

C.  late start date

D.  early start date

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-9738-c0f9-29e3bb5dbe01.html
点击查看答案
63. In which systems development life cycle do model developers use a model to generate functional requirements and physical design specifications simultaneously?

A.  RAD life cycle

B.  Prototyping life cycle

C.  Spiral life cycle

D.  Waterfall life cycle