单选题
)
99. In the Scrum method, during which meeting is the improvement of the product and process
discussed?

A、 sprint retrospective

B、 sprint review

C、 kick-off

D、 daily Scrum

答案:A

试题通
项目管理期末复习WJH
试题通
80. The project cost management knowledge area maps to which process group through the
activities of estimating costs and budget determination?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-fee0-c0f9-29e3bb5dbe01.html
点击查看题目
71. What processes include devising and maintaining a workable scheme to ensure that the project
addresses the organization’s needs?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-eb58-c0f9-29e3bb5dbe01.html
点击查看题目
78. The project schedule management knowledge area maps to which process group through the
activity of schedule control?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-faf8-c0f9-29e3bb5dbe01.html
点击查看题目
190. Which type of power is based on an individual’s personal charisma?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d5b8-c0f9-29e3bb5dbe00.html
点击查看题目
104. Which action involves defining and documenting the features and functions of the products
produced during the project as well as the processes used for creating them?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-2dc0-c0f9-29e3bb5dbe00.html
点击查看题目
44. In a organizational structure, personnel often report to both a functional manager and one or more project managers.
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b4a8-c0f9-29e3bb5dbe00.html
点击查看题目
51. Which characteristic of organizational culture refers to the degree to which departments within
an organization are encouraged to coordinate with each other?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-c060-c0f9-29e3bb5dbe01.html
点击查看题目
101. What important Scrum artifact is used to graphically display progress on each sprint during the monitoring and controlling process?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-25f0-c0f9-29e3bb5dbe01.html
点击查看题目
48. refers to a set of shared assumptions, values, and behaviors that characterize the
functioning of an organization.
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-bc78-c0f9-29e3bb5dbe00.html
点击查看题目
151. After working with key stakeholders to define activities and calculate their resources, what is
the next process in project schedule management?
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8798-c0f9-29e3bb5dbe02.html
点击查看题目
首页
>
IT互联网
>
项目管理期末复习WJH
题目内容
(
单选题
)
手机预览
试题通
项目管理期末复习WJH

99. In the Scrum method, during which meeting is the improvement of the product and process
discussed?

A、 sprint retrospective

B、 sprint review

C、 kick-off

D、 daily Scrum

答案:A

试题通
分享
试题通
试题通
项目管理期末复习WJH
相关题目
80. The project cost management knowledge area maps to which process group through the
activities of estimating costs and budget determination?

A.  initiating

B.  planning

C.  Executing

D.  monitoring and controlling

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-fee0-c0f9-29e3bb5dbe01.html
点击查看答案
71. What processes include devising and maintaining a workable scheme to ensure that the project
addresses the organization’s needs?

A.  Initiating

B.  Planning

C.  Executing

D.  Monitoring and controlling

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-eb58-c0f9-29e3bb5dbe01.html
点击查看答案
78. The project schedule management knowledge area maps to which process group through the
activity of schedule control?

A.  initiating

B.  planning

C.  Executing

D.  monitoring and controlling

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-faf8-c0f9-29e3bb5dbe01.html
点击查看答案
190. Which type of power is based on an individual’s personal charisma?

A.  legitimate

B.  coercive

C.  reward

D.  referent

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-d5b8-c0f9-29e3bb5dbe00.html
点击查看答案
104. Which action involves defining and documenting the features and functions of the products
produced during the project as well as the processes used for creating them?

A.  Collecting requirements

B.  Defining scope

C.  Controlling scope

D.  Validating scope

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-2dc0-c0f9-29e3bb5dbe00.html
点击查看答案
44. In a organizational structure, personnel often report to both a functional manager and one or more project managers.

A.  project

B.  symbolic

C.  matrix

D.  functional

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b4a8-c0f9-29e3bb5dbe00.html
点击查看答案
51. Which characteristic of organizational culture refers to the degree to which departments within
an organization are encouraged to coordinate with each other?

A.  Member identity

B.  People focus

C.  Group emphasis

D.  Unit integration

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-c060-c0f9-29e3bb5dbe01.html
点击查看答案
101. What important Scrum artifact is used to graphically display progress on each sprint during the monitoring and controlling process?

A.  WBS

B.  sprint backlog

C.  burndown chart

D.  product backlog

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-25f0-c0f9-29e3bb5dbe01.html
点击查看答案
48. refers to a set of shared assumptions, values, and behaviors that characterize the
functioning of an organization.

A.  Chain of command

B.  Line of control

C.  Organizational culture

D.  Organizational structure

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-bc78-c0f9-29e3bb5dbe00.html
点击查看答案
151. After working with key stakeholders to define activities and calculate their resources, what is
the next process in project schedule management?

A.  develop the schedule.

B.  control the schedule.

C.  determine their dependencies.

D.  estimate the duration of activities.

https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-8798-c0f9-29e3bb5dbe02.html
点击查看答案