42. In Rizzati Corp, vice presidents in departments such as engineering, manufacturing, IT, and
human resources report directly to the chief executive officer and undertake their tasks
independently of each other. The staffs of these departments have specialized skills in their
respective disciplines. Which type of organizational structure does Rizatti Corp have?
A. Project
B. Symbolic
C. Matrix
D. Functional
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-b0c0-c0f9-29e3bb5dbe00.html
点击查看答案
72. Which processes include acquiring and developing the project team, performing quality
assurance, distributing information, managing stakeholder expectations, and conducting
procurements?
A. monitoring and controlling
B. executing
C. planning
D. initiating
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-ef40-c0f9-29e3bb5dbe00.html
点击查看答案
106. Which action involves normalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables?
A. Creating scope
B. Defining scope
C. Controlling scope
D. Validating scope
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-31a8-c0f9-29e3bb5dbe00.html
点击查看答案
13. Fast tracking is an example of a tool used in management.
A. schedule
B. quality
C. communication
D. risk
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f5-7628-c0f9-29e3bb5dbe00.html
点击查看答案
86. What is the main purpose of project plans?
A. schedule management plans
B. define project scope
C. estimate activity resources
D. guide project execution
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-0a98-c0f9-29e3bb5dbe01.html
点击查看答案
81. Which planning process is within the Project Scope Management knowledge area?
A. Schedule development
B. Developing a project management plan
C. Creation of a WBS
D. Quality planning
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-02c8-c0f9-29e3bb5dbe00.html
点击查看答案
97. Which project would be compatible with the use of the agile approach?
A. Projects with inexperienced and dispersed teams
B. Projects that have a fairly rigid completion date
C. Projects with clear-up front requirements
D. Projects that have more flexible scheduling
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-1e20-c0f9-29e3bb5dbe01.html
点击查看答案
177. Who is best known for distinguishing between motivational factors and hygiene factors when
considering motivation in work settings?
A. Frederick Herzberg
B. David McClelland
C. Abraham Maslow
D. Douglas McGregor
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-ba60-c0f9-29e3bb5dbe01.html
点击查看答案
172. What need is at the highest level in Maslow’s structure?
A. deficiency
B. growth
C. safety
D. physiological
https://www.shititong.cn/cha-kan/shiti/0005ee7e-62f6-b290-c0f9-29e3bb5dbe00.html
点击查看答案
18. A is a tool used in risk management.
A. work breakdown structure
B. project organizational chart
C. critical path analysis
D. probability matrix